28 days of TRU improvement works completed in West Yorkshire
- Region & Route:
- Eastern
Major improvement works modernising the railway between Morley and Dewsbury in West Yorkshire have taken the Transpennine Route Upgrade (TRU) a step closer to delivering faster, more frequent trains on a more reliable and greener network across the North.
Work began on Saturday 30 May and ran until Saturday 27 June. During this period, teams completed a number of improvements including:
- Over 5km of track renewals and over 800m of drainage – improving the reliability of services passing through the area
- Installed 66 OLE (overhead line equipment) masts and fitted 43 OLE foundations – enabling electric trains to run in the future
- Batley station enhancements – improved customer facilities and extended platforms
- Dewsbury station enhancements – strengthened footbridge, extended roof canopies and foundations for extended platforms
- Reconstructed Jack Lane bridge in Dewsbury – strengthening works will enable faster and longer trains carrying more customers over the structure
The transformation of both Dewsbury and Batley stations are now almost complete - both will offer improved accessibility, extended platforms that can accommodate longer trains with more seats, and enhanced facilities for customers travelling across the North.
Jonathan Hepton, project sponsor for TRU, said:
“We’re delighted to have completed this latest series of work safely and on time, thanks to the hard work of our teams and the support of our customers and our communities. TRU has made great strides in delivering a more reliable, electrified railway across the Pennines so far this year, with significant station upgrades delivered, too.
“By the end of summer, we look forward to unveiling a transformed Batley station with a brand-new footbridge, lifts and platforms, which will greatly improve step-free access around the station. At Dewsbury, we will be introducing better waiting facilities and extended platforms.”
“I’d like to say a big thank you to our teams who worked around the clock and throughout the recent very hot weather.”
The focus now shifts to a series of weekend works at Huddersfield station across July and August, in preparation for 16 days of improvement works in September. Customers will be kept on the move via diversionary routes and rail replacement buses on the weekends of July 4-5, July 11-12, July 18-19, July 25-26, and August 1-2. Weekday services remain unaffected.
Liam O’Shaughnessy, TRU Programme Delivery Lead for Northern, said:
“Over the last month, the Transpennine Route Upgrade has made great progress made in in delivering upgrades between Huddersfield and Leeds. The investment in both the infrastructure and improving customer facilities, including at Batley station where improvements will continue this year, will benefit our customers and communities for years to come.
“Working together with partners across the rail industry, we have been able to keep people moving as these works have progressed and we would like to thank everyone for their patience while these works have taken place.”
The weekend improvement works at Huddersfield include:
- Installing a section of the new station roof
- Tarmacking the new platform extensions at the Leeds-end of the station
- Installing and testing the new lifts
- Extending the new footbridge and the existing subway
Notes to Editors
Notes to Editors
A series of road closures will also be in place in the Huddersfield area to facilitate TRU work. Please visit https://thetrupgrade.co.uk/yourstation/huddersfield/ to view these in full.
TRU fast facts
- 25% of the route is now electrified, with electric train services now running between Manchester and Stalybridge, and York and Church Fenton
- Once complete, TRU aims to halve the time lost to delays
- There are currently 70 worksites across the 70-mile route
- TRU will deliver:
- The full electrification of the line
- Double the amount of tracks in key locations, allowing fast trains to overtake stopping services
- Implement digital signalling to increase speed and capacity
- Improve all 23 stations on the route, supporting accessibility
- TRU has over 5000 staff, with 85% coming from within 40 miles of the route – TRU will have created over 8000 jobs across the duration of the programme
- TRU is expanding freight provision, opening 15 extra freight paths and widening tunnels so shipping containers can travel between ports on the east and west coasts via rail, removing over 1000 lorries a day from the busy roads across the Pennines
Key milestones to date
- New station built at Mirfield
- New station built at Morley
- Introduction of a fully accessible platform 2 at Castleford station to support diverted services between York and Manchester
- £100m upgrade of diversionary routes completed ahead of major works across the Transpennine Route, increasing railway resilience
- Upgrade of Hope Valley line complete, with a second platform built at Dore & Totley, as well as 1km of additional track at Bamford to reduce bottlenecks
As discussed, I'd remove this and just add a line in the main PR to say that to facilitate our works, there are some highways changes so check the TRU Huddersfield page
Contact information
Passengers / community members
Network Rail national helpline
03457 11 41 41
Latest travel advice
Please visit National Rail Enquiries
Journalists
Ewan Bayliss
Communications Executive
Network Rail
ewan.bayliss@networkrail.co.uk
About Network Rail
We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.
Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.
Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk