Thursday 19 Dec 2024
2024 wrap-up: a landmark year for TRU
- Region & Route:
- Eastern
With 2025 approaching, TRU would like to thank customers for their support as the programme reflects on a successful year that saw several key milestones achieved.
The newly appointed Chancellor of the Exchequer reaffirmed the Government’s commitment to the Transpennine Route Upgrade in October’s Autumn Budget announcement. Just a week later, the Chancellor, along with the Transport Secretary and Mayor Andy Burnham, visited Manchester and Stalybridge to see first-hand the progress being made on the programme.
A major target for TRU in 2024 was achieved in November, as TransPennine Express joined Northern in operating electric passenger services between Manchester Victoria and Stalybridge. This was a huge step forward in the programme’s aims to deliver faster, more frequent trains on a cleaner, greener, more reliable railway.
Electric test trains have also been in operation between York and Church Fenton, with the first electrified passenger services to launch in 2025.
Significant progress has also been made in upgrading infrastructure across the route, with perhaps the most noticeable change seen at the iconic Huddersfield station.
The station upgrade has just passed the one-year mark. Scaffold towers and a raised working platform are in place to enable the trainshed canopy restoration work, whilst the tearoom – built in 1886 – has been dismantled in 8,000 different pieces and carefully stored away ahead of being reinstated in the future.
A new, purpose-built office compound was also opened at the rear of the station, so that the programme had a central working hub at such a vital location on the route. Named HD1, the sustainable approach to the building of the office compound contributed to TRU’s perfect 45/45 score in a Considerate Constructors Scheme assessment of the station.
October saw the completion of TRU’s public consultation on plans for rail upgrades between Stalybridge and Diggle (Saddleworth). More than 300 residents gave feedback on proposals, including major upgrades at both Mossley and Greenfield that will make the stations fully accessible for the first time.
The programme was granted a Transport and Works Act Order (TWAO) to bring further upgrades to the route between Leeds and Micklefield, outlining plans to replace five level crossings with safer alternatives, work to a number of bridges to enable electrification, and the installation of some small-scale infrastructure.
Back in March, TRU announced a £100m investment for a new rail depot in Shipley which will be used to house and maintain Northern’s fleet of electric trains on the Airedale and Wharfedale Lines whilst access in and out of their Neville Hill depot in Leeds is restricted during a future phase of TRU works. Northern will keep the depot open following the completion of upgrades, with as many as 100 permanent employees.
Elsewhere in West Yorkshire, the new year brought an intriguing find – following investigations at a TRU site near Ravensthorpe Road, a team from Oxford Archaeology believed that a large, irregularly shaped cropmark was probably an Iron Age or Romano-British enclosure.
A collection of Romano-British ceramics, building materials, flint, glass and animal bones were all recovered at the site and are still in testing.
TRU closed out the year with the launch of the programme’s first annual Sustainable Development Report, based on the sustainability strategy, ‘Our Guiding Compass’.
Our Guiding Compass has been instrumental in shaping TRU’s sustainable development efforts, comprising of four key pillars that steer sustainability: Northern jobs, enhanced environment, satisfied customers, and community engagement.
One milestone of many outlined in the report was the introduction of PlanBEE Rail, a unique higher apprenticeship scheme designed to recruit and nurture the next generation of multi-disciplinary project managers. In what is a two-year programme where the apprentices rotate around four different employers, the TRU cohort have already had a taste of what’s it’s like to be part of a multi-billion-pound railway programme.
As part of the programme’s commitment to leave a long-lasting legacy within the communities it operates, 2024 saw the introduction of the £175,000 TRU Community Fund. The fund offers community groups, schools and charities the opportunity to create or enhance indoor or outdoor community-focussed facilities through small (£1000-£5000) or medium (£5000-£20,000) grants, with the successful recipients recently confirmed.
Work to deliver upgrades across the route continues over the Christmas period, too:
- Railway bridge deck replacement in Osmondthorpe, on the east side of Leeds with a stronger structure that will enable the tracks to be moved into a better position and allow faster, longer trains to run.
- Foundation piling in Church Fenton for new overhead line equipment (OLE), which will enable electric trains to be introduced in the future.
- The removal of a section of Station Road railway bridge in Mirfield, opening up the station wall to create a new station entrance, and carrying out piling for a new station platform.
- Track point replacement near Miles Platting in Manchester, to allow trains to change from one line to another.
Gordon Kells, TRU Interim Managing Director, said:
“2024 was a big year for TRU and I’m really proud of what’s been achieved across the programme. A number of key milestones have been reached and we’ve paved the way for more success next year.
“I’d like to thank all of our passengers, stakeholders and local communities for their understanding and support and we are looking ahead to further achievements in 2025.”
Notes to Editors
TRU will bring passengers:
• More trains to choose from and more seats. Our improvements will enable more
trains to run between Manchester, Huddersfield, Leeds and York with up to six fast
services every hour between Leeds and Manchester and up to two stopping
services for local connectivity.
• Faster journeys so you can travel to your favourite towns and cities more quickly.
Our fastest journey times are forecast to be 63-66 minutes between Manchester
and York and 41-42 minutes between Manchester and Leeds.
• More reliable journeys with trains that run on-time
• Better stations across the Transpennine route, bringing passengers a better travel
experience through improved, more accessible stations
• Greener travel, reducing our carbon footprint and improving air quality. Our plans
aim to save up to 87,000 tonnes of carbon emissions each year – supporting the
government’s Net Zero objectives. We’re also developing a proposal to move more
goods by rail (up to 15 more freight trains each day.)
• Together, these freight trains are expected to remove over 1,000 lorries off the road each day.
TRU will bring local communities:
• Jobs for local people. Our workforce will be local, with 80% employment from
within a 40-mile radius of the route, and 60% employment from within a 25-mile
radius. With a current workforce of around 2000 people, we estimate that could
double over the course of the programme. We’ll employ an apprentice for every
£4million spent.
• Improved natural environments near the railway through 10% biodiversity net
gain across the route. This will create or enhance habitats for wildlife.
The multi-billion-pound Transpennine Route Upgrade (TRU) will bring this line into the
21st century with 70-miles of fully electric, digital railway. Our plans include:
• Electrifying the whole route between Manchester and York via Huddersfield and
Leeds
• Installing a new digital signalling system along the Transpennine route
• Doubling the number of tracks from two to four between Huddersfield and
Westtown in Dewsbury.
• Station improvements along the route to enhance customer experience, comfort
and accessibility
• Improving the railway on diversionary routes to allow more trains to run, to help
keep passengers and freight moving while the core Transpennine route is closed to
deliver essential upgrades. This will provide capacity and reliability improvements
for future too.
Contact information
Passengers / community members
Network Rail national helpline
03457 11 41 41
Latest travel advice
Please visit National Rail Enquiries
Journalists
Ewan Bayliss
Communications Executive
Network Rail
ewan.bayliss@networkrail.co.uk
About Network Rail
We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.
Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.
Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk