16 days of TRU improvement works completed in Huddersfield: 26-379

Monday 5 Oct 2026

16 days of TRU improvement works completed in Huddersfield

Region & Route:
Eastern

Major improvement works delivered by the Transpennine Route Upgrade (TRU) in Huddersfield have taken the programme a significant step closer to delivering faster, more frequent and more reliable rail services for customers travelling across the North.

Work took place between Saturday 19 September and Sunday 4 October, during which engineers worked around the clock to complete a series of major upgrades across the railway and at both Huddersfield and Deighton stations. 

During the 16-day programme of works, teams completed: 

  • Installation of two new lines of track through the Huddersfield area, including more than 2km of new track, supporting future capacity improvements and enabling faster services to overtake stopping trains 
  • More than 1.3km of track renewals and over 900m of drainage renewals to improve the reliability of services 
  • Significant progress at Huddersfield station, including platform extensions, new restoration of the station's historic roof canopy and subway extensions 
  • Major upgrades at Deighton station, including work to extend the platforms and the  installation of a new accessible footbridge which will have lifts once complete  
  • Installation of more than 50 overhead line equipment masts and over 50 steel structures to support future railway electrification. 
  • Preparation works at A62 Leeds Road bridge ahead of its future reconstruction to accommodate railway electrification 
  • Signalling installation to improve railway performance and reliability 

 

James Richarson, TRU Managing Director, said:

“Completing this latest phase of work is down to the dedication, skill, and teamwork of our teams. From infrastructure delivery to planning and keeping passengers on the move during the disruption to their journeys, every part of the programme has played a role in this latest work.” 

 

Liam O’Shaughnessy, TRU Programme Delivery Lead for Northern, said: 

“The work that has been completed over the last 16 days in the Huddersfield area is another crucial step towards delivering the benefits that the Transpennine Route Upgrade will bring for customers across the North.

“We have worked closely with our industry partners to keep customers on the move as these works have continued and we would like to thank our customers and local communities for their patience and cooperation whilst these improvement works have been taking place.”

 

Following this successful programme of works, attention will now turn to the next phase of delivery, including a 38-day closure of Huddersfield station starting after the final service on Thursday 24 December 2026 until Sunday 31 January 2027, reopening on Monday 1 February 2027, when engineers will carry out further transformative upgrades to the railway and station. 

These upgrades form part of the wider multi-billion-pound TRU programme, which is transforming the railway between Manchester, Huddersfield, Leeds and York by improving capacity, reliability and accessibility while supporting the future introduction of cleaner electric trains. 

Notes to Editors

Following the completion of the 16-day closure, further work will take place at Huddersfield station to complete the main station upgrades by early 2027. This includes closures of Huddersfield station over the following weekends: 

  • Saturday 10 & Sunday 11 October 2026 
  • Saturday 14 & Sunday 15 November 2026 
  • Sunday 13 December 2026 
  • Sunday 20 December 2026 
  • A 38-day closure of Huddersfield station following the final service on Thursday 24 December 2026 until Sunday 31 January 2027, reopening on Monday 1 February 2027

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Ewan Bayliss
Communications Executive
Network Rail
ewan.bayliss@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk