Work under way to repair collapsed tunnel in Howden: The collapsed road at Howden, 18 April

Tuesday 19 Apr 2016

Work under way to repair collapsed tunnel in Howden

Region & Route:

A collapsed water tunnel near Howden which has led to the closure of the A614 will be fully rebuilt in around five weeks.

The culvert, which carries water alongside the railway and under the road, suffered a partial collapse in the early hours of last Thursday morning which led to the immediate closure of both carriageways, although the railway is far enough away from the site that it is unaffected by the incident.

The cause of the collapse remains under investigation, but work has already begun to replace the tunnel with a new structure and get the road reopened fully in around five weeks, with the plan to partially open the road sooner to allow single file traffic to pass through.

Mark Tarry, area director for Network Rail, which owns the structure, said: “Safely carrying out structural repairs to tunnels like this one is something we are very experienced in and work has already started to get the tunnel rebuilt and the road reopened. I’d like to thank those living in Howden or who would normally travel along the A614 for their patience and understanding while the repair project is carried out, with our teams working 24/7 to get the road reopened as soon as possible.”

Network Rail continues to work closely with both Yorkshire Water and East Riding of Yorkshire Council on all elements of the project, with an emergency diversion route currently in place for vehicles travelling through the area.

 

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Network Rail press office - Toby Higgins
Head of Communications
Network Rail
0330 333 1800
toby.higgins@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk