Thursday 10 Jul 2014
Work to start to replace footbridge and improve platforms at Hartford station
- Region & Route:
Work will begin this weekend to provide passengers with better platforms and a new footbridge at Hartford station.
Network Rail will be removing the existing footbridge at the station on Saturday night (12 July) using a 1,000 tonne crane which will lift the structure over the platforms into the station car park where it will be dismantled and removed.
The size of the bridge and the equipment needed to remove it means the station’s car park and the A559 Chester Road will be closed between 0730 on Saturday 12 July and 2359 on Sunday 13 July. The railway will remain open during the work and there will be no impact on services.
The new footbridge will be installed and all improvements at the station – including resurfaced platforms and a new roof on the station building – will be completed for use by the autumn. Access to all platforms will be maintained while the footbridge is being replaced.
Ian Joslin, area director for Network Rail, said: “The new footbridge and improved platforms will provide passengers with a better experience and environment at Hartford station. As passenger numbers continue to rise, it is essential that we invest in the network to meet the increased demand being placed on it.
“We have carefully planned the work to cause the minimum amount of disruption and train services will continue to run as normal throughout.”
David Whitley, London Midland’s head of regional services, said: “This is excellent news for passengers and I’m really pleased, given the scale of the work involved, that this is being carried out without any disruption to rail services.
“We have been working hard to communicate the message that the car park will close and I apologise to passengers for the temporary disruption this may cause.”
For information contact Network Rail’s national helpline on 08457 114 141.
Contact information
Passengers / community members
Network Rail national helpline
03457 11 41 41
Latest travel advice
Please visit National Rail Enquiries
Journalists
Network Rail press office - North West & Central Region
0330 854 0100
NWCmediarelations@networkrail.co.uk
About Network Rail
We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.
Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.
Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk