West Coastway passengers advised to plan ahead for half-term closure: Barnham station

Monday 30 Sep 2019

West Coastway passengers advised to plan ahead for half-term closure

Network Rail has today reminded passengers in West Sussex and Hampshire that a multi-million-pound upgrade of the lines between Barnham, Chichester and Havant starts in four weeks

The work will involve closing the line over nine days during the autumn half-term, plus two Sundays and one further weekend, to allow 2.3km of new track to be laid and improvement work at several level crossings on the route.

The planned dates for work are:

  • Nine days from Saturday 26 October to Sunday 3 November inclusive
  • Sunday 10 November
  • Sunday 17 November
  • Saturday 30 November and Sunday 1 December

Paul Harwood, Investment Director, Network Rail Southern said: “Our information campaign has been underway for several weeks, but we will be stepping this up even more between now and the closure dates. We want to ensure that passengers are aware of the work and of the alternative transport arrangements which will be in place.”

He added: “We are working closely with the train operators, local councils and businesses to ensure that people are aware of the work and of the alternative transport arrangements which will be in place.

“Opting for this closure is the most efficient and least disruptive approach. The alternative would be many weekends of disruption. Once complete the work will improve the reliability of rail services on the line reducing delays for passengers.”

During the weekdays, from Monday 28 October to Friday 1 November 2019, buses will replace trains between Havant and Chichester and journeys will take longer than usual.

On the weekend dates the line between Havant and Barnham will be closed, meaning buses will replace trains between those stations on each date affected. Work on the level crossings will result in some diversions on local roads.

Throughout the work there will be no Southern trains west of Havant to Portsmouth or Southampton. Great Western Railway services to/from Brighton will run to/from Portsmouth instead. Trains to London will still run from Havant (to London Waterloo via South Western Railway) and Bognor Regis (via Southern). During the week days, trains to London will also run from Chichester (via Southern).

Keith Jipps, Infrastructure Director at Southern’s parent company Govia Thameslink Railway, said: “Our Southern services will be significantly affected by this vital work to improve reliability and passengers should check ahead and allow longer for their journeys.”

Notes to Editors

Notes for editors:

  • The stations directly affected by the closure will be: Barnham, Chichester, Fishbourne, Bosham, Nutbourne, Southbourne, Emsworth, Warblington, Havant
  • There is an impact on 15 level crossings, and two footpath crossings.
  • A traffic management plan will be in place, and consideration has been given to accessibility for pedestrian level crossing users.

Buses will generally run as follows:

  • Barnham/Chichester to Havant calling at all stations – up to four per hour
  • Barnham/Chichester to Havant non-stop or limited stop – two per hour
  • Chichester to Fareham calling at Havant only – two per hour on Monday to Friday onlyFor detailed bus times check www.nationalrail.co.uk nearer the time.

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Tony Henderson
tony.henderson@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk