West Coast main line reopens after nine-day project: West Coast main line blockade work - July 2013

Tuesday 23 Jul 2013

West Coast main line reopens after nine-day project

Region & Route:

Major improvements to the West Coast main line between Warrington and Preston were successfully completed on Monday morning after nine consecutive days of engineering. Four junctions - Golborne, Bamfurlong, Wigan Springs Branch and Balshaw Lane - were replaced and three miles of track re-laid to help increase line speeds and make journeys more reliable.

During one of the hottest weeks of the year, a team of 720 men and women were on site 24 hours a day to deliver this significant investment. Over 900 barrels of water were consumed and 3,000 bottles of sun cream used as track temperatures rose as high as 46C.

Train services resumed on Monday morning and were running at a speed of 80mph across one of the new junctions. This is the first time Network Rail has been able to reopen lines at this speed following major engineering work.

Martin Frobisher, area director for Network Rail, said: "I was in the cab of the first test train over the line this morning and I’m pleased that under some tough weather conditions we’ve been able to deliver on time, this vital improvement which will make journeys on the west coast main line more reliable and punctual. I would like to thank passengers for their support and cooperation during the closure, as well as our industry partners who we worked very closely with to prepare for and deliver this critical project."

Usually, Network Rail would have carried out work of this kind over a number of bank holiday weekends requiring train services to be replaced repeatedly by alternative transport. By carrying out the work in a nine-day continuous spell this summer, engineers were able to complete the replacement of four junctions around 16 months earlier to avoid disrupting rail travel plans for many weekends and nine bank holidays over the next two years.

Why did we do it?

The blockade was part of a major process along the length of the WCML to improve reliability and cut the amount of the time the railway needs to close. The layout of the junctions between Warrington and Preston was such that tamping them required a weekend closure every year. This is because the points were set "toe-to-toe", requiring special tamping. By stretching Network Rail has also removed switch diamonds, which are difficult to maintain. They are also, appropriately enough, vulnerable to high temperatures and need constant monitoring in key locations in hot weather.

Speeds over the junctions were also increased to match line speeds on diverging routes. For example, diverging trains at Golborne Junction used to approach at 90mph, slow to 50mph, before accelerating to 75mph once across the junction. Now they travel across the junction at 75. There was an even greater jump at Balshaw Lane, where trains approached at 110 (125 EPS) and slowed to 50, before accelerating to 75 on the down slow.

Phil Bearpark, Production Director for Virgin Trains said: "I congratulate the engineering team at Network Rail for completing this very challenging piece of work on time. A key section of the West Coast Main Line will now immediately provide better reliability for our customers and in the longer term is another stepping stone in our quest for faster journey times for Anglo Scottish services"

Notes to editors

The project by numbers:

3 miles of track to renew

4 main line junctions upgraded

18 miles of West Coast Main Line

6,600 new railway sleepers laid

21,500 tonnes of ballast

Materials delivered by 61 trains in 865 wagons

Network Rail worked with the train operators to arrange a replacement rail and road travel service and our joint aim was to enable passengers to travel by train as far as possible.

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Network Rail press office - North West & Central Region
0330 854 0100
NWCmediarelations@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk