Thursday 2 Jan 2014
Trains resume at Manchester Victoria after successful Christmas rail upgrade
- Region & Route:
A major upgrade of the railway at Manchester Victoria over the Christmas and New Year holiday has been completed, with rail services resuming as planned on Thursday morning.
The closure allowed Network Rail engineers to install the equipment that will allow electric trains to start running from Manchester Victoria to Liverpool next December as part of the £400m North West Electrification Programme.
Network Rail engineers spent 10,000 man hours over the Christmas and New Year period, installing 74 foundations and some of the steel work for the overhead line equipment which will allow electric trains to operate. In the station, engineers installed 42 fixtures to hold the overhead wires to the roof of station.
At the east of the station, under Cheetham Hill road bridge, 400m of track was removed to allow the track to be lowered by up to 17 cm to create the headroom required for overhead lines. This required 1300 tonnes of spoil to be removed before the track was re-laid with almost 1000 tonnes of new ballast. Meanwhile, work continued on the £44m project to renovate the station and install the new roof which will be completed later this year.
To allow the project to be completed safely, there will be further planned closures to allow Network Rail engineers to complete the electrification work, with no rail services operating through Manchester Victoria on Sundays until the end of May. Customers are being advised to check travel details thoroughly when booking tickets and before they travel.
Martin Frobisher, area director for Network Rail, said: “Our engineers have sucessfully completed much of the work to allow electric trains to run from Manchester to Liverpool starting from December this year, providing passengers with quicker, cleaner and more frequent services. They did this despite some very difficult weather over the Christmas and New Year holiday.
“This project represents a significant investment in the railway in Manchester and, in conjunction with the Northern Hub, will see more trains and faster journeys, improving travel between major towns and cities across the north.
“In order to complete this on time and allow our engineers to complete the electrification of the railway through Manchester Victoria, we will need access to the railway on Sundays until the end of May. We thank passengers for their patience while we carry out this vital upgrade.”
Lee Wasnidge, area director for Northern Rail, said: “The rail network around Manchester has been a hive of activity over the festive period and work will continue in the New Year. With the electrification of routes into the city and further progress on the redevelopment of Manchester Victoria, 2014 will bring significant improvements for passengers.”
Full details of Sunday service changes are available in Northern Rail timetables:
- A shuttle bus will operate between Manchester Victoria and Salford Crescent
- Services from Chorley / Clitheroe / Wigan will divert to Manchester Oxford Road
- A shuttle service will operate between Manchester Victoria and Rochdale until 9 February
Notes to editors
Full details of amended timetables, alternative travel options and walking routes will be available shortly from www.northernrail.org and www. tfgm.co.uk
Contact information
Passengers / community members
Network Rail national helpline
03457 11 41 41
Latest travel advice
Please visit National Rail Enquiries
Journalists
Network Rail press office - North West & Central Region
0330 854 0100
NWCmediarelations@networkrail.co.uk
About Network Rail
We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.
Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.
Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk