Train services resume on the Preston-Bolton-Manchester railway as upgrade nears completion: Team Orange installing power cables to supply new overhead equipment with electricity

Monday 3 Sep 2018

Train services resume on the Preston-Bolton-Manchester railway as upgrade nears completion

Region & Route:
| North West & Central

Mid-week train services between Preston, Bolton and Manchester have resumed today (Monday 3 September) after a nine-day closure to allow engineering work to take place along the route.

As part of the rail industry’s multi-billion-pound Great North Rail Project, the route between Manchester and Preston is being upgraded to enable better and more reliable electric trains to run.

Over the past nine days, Network Rail’s Team Orange has been working round-the-clock to install overhead electric wires and carry out adjustments to several station platforms on the route.

To date, engineers have installed 78 wire runs out of a total 98. The wires are being attached to more than 1500 newly installed steel structures and will supply power to greener and quieter electric trains.

To complete the upgrade of the railway through Bolton, Team Orange will continue mid-week overnight working and weekend working until Sunday 4 November.

Martin Frobisher, route managing director at Network Rail said: “We are very grateful for passengers’ continued patience over the last nine days which has allowed us to make excellent progress on the Bolton corridor, as part of the Great North Rail Project.

“This vital work will enable electric-powered, greener, faster, more frequent, more spacious and more reliable trains to run between Manchester and Preston.”

For more information on the Great North Rail Project and Railway Upgrade Plan visit: https://www.networkrail.co.uk/our-railway-upgrade-plan/key-projects/great-north-rail-project/

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Network Rail press office - North West & Central Region
07740 782954
NWCmediarelations@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk