SIX MONTH COUNTDOWN TO NEW STREET’S HALF TIME SWITCHOVER

Region & Route:

Passengers using Birmingham New Street will see the first major changes in over 40 years when the station concourse switches over next April, marking the half way point of the redevelopment.

 

In six months time, the existing station concourse and its entrances which have been in use since the 1960s will close overnight to allow the first half of the brand new concourse to open to passengers.

Chris Montgomery, Network Rail project director said: “We’ve committed to keeping New Street open to passengers throughout the redevelopment and to date, we’ve been able to do most of our work behind the scenes.

“The switchover next year will be the first time passengers see real changes in how they use and access New Street station. By switching off the old station and opening the first half of the new concourse next door, we can keep passengers moving through New Street while we continue rebuilding the existing half of the station and shopping centre above.”

A public information campaign will kick off in January to inform passengers about the changes they can expect to see at New Street in April 2013. In the meantime, passengers will be able to find out more at a public exhibition at the station next week which will be open between 7am-7pm on Monday 8, Tuesday 9 and Wednesday 10 October.

Sir Albert Bore, leader of Birmingham City Council, said: “The refurbished Birmingham New Street station will provide a much improved transport interchange for the 140,000 passengers who use it every day and these changes are designed to keep passengers and trains moving while this major work goes ahead. This is a vital project for the city, stimulating economic growth and regeneration and, in the newly-named Grand Central, it will provide one of the best-connected retail spaces in the country.

Around 1000 construction workers are currently on site at New Street, main areas of activity include:

Platforms: Platforms are refurbished one at a time, leaving the other 11 platforms open to allow a full train service to run. Platform 11 is currently closed and will reopen on Sunday 7 October when work will move to Platform 8.

Moor Street Link: This new pedestrian route will open alongside the new concourse in April 2013 providing a link between Moor Street station and the new concourse via Stephenson Street.

Pallasades/Southside: Demolition is ongoing in several areas including the old car park and the centre of the building to form the new atrium which will open in 2015. The Pallasades remains open throughout the redevelopment. On the south side of the station, construction of the John Lewis department store is well underway.

Façade: The first sections of stainless steel façade will be installed later this autumn, above Stephenson Street on the north side of the station.

Cllr Roger Horton, Centro’s lead member for transforming rail, said: “I’m very pleased that the Gateway project remains on course and on time, and its completion will be a massive boost for the thousands of passengers using the station each day.

“The concourse switchover will be a key milestone in the station’s transformation which in turn will help underpin our efforts to create a world class transport system for the West Midlands.”

New concourse facts:

  • When the first half of the new concourse opens it will have all of the facilities expected in a major station with a new bigger and improved ticket office plus improved access with new up and down escalators and lifts to every platform.
  • Navigation Street footbridge at the west end of the station will close to passengers temporarily as new entrances will open onto Stephenson Street and Hill Street.
  • There will also be new escalators up to the Pallasades to replace the existing ones which will close to allow the old concourse to be rebuilt.
  • All vehicle traffic will move from Smallbrook Queensway on the east side of the station across to Hill Street with the taxi rank temporarily moving to Navigation Street.

Notes to editors

The redevelopment of Birmingham New Street station and the Pallasades Shopping Centre is backed by Birmingham City Council, Network Rail, Department for Transport, Centro and Advantage West Midlands.

Network Rail is delivering the project alongside its delivery partner Mace.

Upon completion in 2015, the project will deliver:

Space to accommodate passenger growth: the new concourse will be three and a half times bigger than at present and will be enclosed by a giant atrium which will flood the station concourse and shopping centre with natural light.

Better access for all: over 30 new escalators and 15 new public lifts will make it much easier to travel between the platforms and the concourse above.

Cutting edge design: a stunning new station façade will create a new landmark building in the heart of Birmingham.

A revitalised city centre: the new Grand Central Birmingham anchored by the John Lewis department store will offer new retail brands alongside quality places to eat and drink, cementing Birmingham’s reputation as one of the UK’s top retail destinations.

Regeneration and economic growth: new pedestrian links will open up the city centre, stimulating regeneration and creating new jobs. We’re also working to open up job opportunities to the local workforce during construction.

The station will remain open throughout the redevelopment.

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Network Rail press office - North West & Central Region
0330 854 0100
NWCmediarelations@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk