Monday 12 Aug 2019

Shrewsbury station upgrade continues

Region & Route:
Wales & Western: Wales & Borders

Work to upgrade Shrewsbury station continues with repairs and the renewal of station canopies almost complete and work progressing on the refurbishment of Dana footbridge.

Network Rail teams have been carrying out essential repairs to the station canopies over platforms 4, 5, 6 and 7 and this work is due to be completed later this month.

Work to refurbish and strengthen Dana footbridge, which began in December 2018, also continues. Engineers uncovered extensive steel work repairs that were required to strengthen the footbridge as well as brick and timber repairs and replacements on the structure. The windows on the footbridge are also being replaced and the deck walkway is being renewed with an anti-slip surface. The structure will be deep cleaned, surfaces grit blasted and re-painted, ensuring that the appearance of the footbridge is improved.

Work is expected to be complete on the listed footbridge by November 2019.

Chris Wildy, works delivery manager for Network Rail in Wales and Borders said: “We understand these structures are part of the historic fabric of Shrewsbury station and this upgrade work will see the historic station refreshed for the benefit of passengers and the local community.

“While refurbishing Dana footbridge our engineers uncovered much more extensive steel work repairs that were required to strengthen the structure and our teams have been working very hard to complete these essential repairs.

“We would like to thank the local community and passengers for their patience while we continue to carry out this work and assure them that we are doing all we can to keep disruption to a minimum and complete this essential work as soon as possible.”

This latest phase of canopy work has been part-funded by the Railway Heritage Trust.

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Steven Crane-Jenkins
Media Relations Manager
Network Rail (Wales and Borders)
07732 643228
Steven.Crane-Jenkins@NetworkRail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk