Friday 14 Jun 2013
Selby swing bridge improvement works
- Region & Route:
Improvements to Selby swing bridge and two rail bridges in Hull have been re-planned following a spoil heap slip on the main diversionary route. The rail industry has worked together to re-plan the work in order to minimise the impact on the travelling public.
Phil Verster, route managing director for Network Rail, explained: "Two years ago we began to plan the most significant refurbishment of Selby swing bridge since it was built in 1889. This work would mean that no trains would be able to run through Selby. Therefore, we planned to complete the renewal of other bridges in the Hull area, as well as level crossing and track improvements, at the same time. In bundling the work together in this way we would only disrupt the line once, minimising the impact on passengers.
"This plan was reliant upon using a diversionary route via Hatfield & Stainforth to maintain a train service to Hull. Unfortunately, the extraordinary events at Hatfield Colliery made it unworkable and the projects in Selby and those affecting passenger services to Hull were deferred. The work on Selby swing bridge has been reprogrammed for next summer. However we will need to complete work on other bridges and tracks over three consecutive weekends from 5 October 2013 in order to keep services on the route running reliably until then."
During each of the weekends intensive maintenance will also be carried out on Selby swing bridge to keep the structure operational until the full, re-programmed work between 26 July and 7 September 2014.
Weekend of 5 October 2013
Buses will replace trains:
Between Selby/Goole and Hull 23.30 Friday – 23.10Saturday
Between Leeds and Hull 23.10 Saturday to 05.30 Monday
Work is planned to include:
Reconstruction of Selby swing bridge span 1 (over the road)
Track maintenance works on Selby swing bridge
Dairycoates intersection bridge, Hull - first part of waybeam renewal
Market Weighton canal bridge reconstruction
Gascoigne Wood track renewal phase 1
Weekend of 12 October 2013
Buses will replace trains:
Between Selby/Goole and Hull 23.30 Friday – 23.10Saturday
Between Leeds and Hull 23.10 Saturday to 05.30 Monday
In addition to work on Selby swing bridge work is planned to include:
Dairycoates intersection bridge, Hull – second part of waybeam renewal
Gascoigne Wood track renewal phase 2
Weekend of 19 October 2013
Buses will replace trains:
Between Selby/Goole and Hull 23.30 Friday – 23.10Saturday
Between Leeds and Hull 23.10 Saturday to 05.30 Monday
In addition to work on Selby swing bridge work will is planned to include track works at Caville bridge
Richard Allan, area director, Northern Rail, said: The landslip at Hatfield & Stainforth created a unique situation impacting on planned improvement work. We fully support the steps taken to reschedule some work to make sure diversionary routes are available and the necessity to carry out some activity in October to make sure we can keep providing a reliable service for customers. We’ll be keeping customers updated on information about the October amended plans via our website and at stations.”
Notes to editors
This programme is entirely dependent upon the restoration of passenger services through Hatfield & Stainforth, currently planned for 8 July 2013. Should the restoration of services at Hatfield be delayed to coincide with the planned work at Selby and Hull, this will again be re-planned.
Bridge works at Spring Bank West and James Ricketts Avenue are going ahead this August. Both of these structures are on the freight line so passenger services are unaffected. Work at James Reckitt Avenue is planned for 17/18 August and the work at Spring Bank West on bank holiday weekend.
Please note: The press office phone line is currently out of order. Please call 07919 128645 with any enquiries on 14.6.13
Contact information
Passengers / community members
Network Rail national helpline
03457 11 41 41
Latest travel advice
Please visit National Rail Enquiries
Journalists
Network Rail press office -London North Eastern & East Midlands route
01904 383180
mediarelations@networkrail.co.uk
About Network Rail
We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.
Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.
Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk