Rugeley Trent Valley to Walsall electrification work is well underway: Chase line electrification - Walsall - Copy

Friday 18 Aug 2017

Rugeley Trent Valley to Walsall electrification work is well underway

Region & Route:
| North West & Central

Improvements to the railway between Rugeley Trent Valley and Walsall are progressing as planned as Network Rail engineers continue work to electrify the Chase line.

Over the past six days, engineers have carried out a range of work including installing 52 steel structures to support the overhead lines which will power electric trains, refurbishing existing power lines south of Walsall station and installing over 25 concrete foundations ready for steel stanchions to be installed. Vegetation has been cut back, 120m of new drainage has been put in and the railway tunnel under Walsall has been inspected.

The line will reopen on Tuesday 29 August after a 16 day closure as part of Network Rail’s national Railway Upgrade Plan which is seeing more than £100m invested in the Chase line.

An increasing number of passengers use the Chase line each year and improvements are needed to accommodate this growth. Overhead wires are currently only installed as far as Walsall which means London Midland currently runs diesel trains from Birmingham to Rugeley Trent Valley. Once fully electrified, passengers will benefit from a cleaner, greener, quieter and more reliable railway between Birmingham and Rugeley with more frequent services.

Over the next 10 days the remaining steel structures will be installed, more of the existing overhead power lines will be replaced and 2800m of rail will be replaced.

Martin Tiller, Network Rail’s project sponsor, said: “This work, part of our Railway Upgrade Plan, will mean passengers travelling between Rugeley and Birmingham via Walsall will have a better, more reliable railway.

“The work is going to plan and we are progressing well. Unfortunately these upgrades cannot be done while trains are running so we have had to close the line between Walsall and Rugeley Trent Valley for 16 days. The work has been carefully planned with London Midland to get the maximum amount completed whilst causing the least disruption. I would like to thank passengers for their patience while we carry out these upgrades to deliver a better railway.”

Amanda Milling, MP for Cannock Chase said: "I completely understand that passengers will be very concerned about the disruption on the Chase Line in the coming weeks but they will enjoy a much better service once the electrification is complete.  The electrification of the Chase Line will see faster and more frequent trains which mean there are hundreds more seats, bringing an end to the misery passengers have faced over the last few years.  I would urge passengers to check before they travel as there will be an amended timetable with a replacement bus service."

London Midland’s head of Route, Rob Hornsey, said: “We would much sooner be running trains than buses in August but it will be worth it when we can run more frequent, cleaner, quieter and quicker trains to carry more people when the work is done. I’d like to thank all our passengers and neighbours for their patience and understanding while this exciting project to upgrade the Chase Line progresses.”

The closure in numbers:

  • 16 days of closure
  • Over 100 new steel structures installed
  • 14 engineering trains used
  • 500m of troughing put in
  • 2,800m of rail replaced
  • 20,000 tonnes of aggregates used
  • 6 gantries erected
  • 12+ pre cast concrete bases installed
  • 40 piles installed
  • 20 concrete foundations installed
  • 2 electricity substation developed
  • Nearly 200,000 track components used
  • 1,250m of geotextile matting installed under the track

The closure has been carefully planned with London Midland. Work which will take place includes:

  • Replacing and realigning the track at various locations between Walsall and Rugeley Trent Valley
  • Temporary closure of Bloxwich level crossing. A diversionary route for road traffic and pedestrians will be in place
  • Temporary closure of Landywood and Stoneyfields footpath crossings
  • Piling to install remaining foundations for stanchions
  • Installation of stanchions and gantries ahead of overhead lines being installed in 2018

From Sunday 13 August until Monday 21 August buses will replace trains between Tame Bridge Parkway, Walsall and Rugeley Trent Valley to an amended timetable

From Tuesday 22 August until Monday 28 August buses will replace trains between Walsall and Rugeley Trent Valley to an amended timetable.

For more information on the work visit: https://www.networkrail.co.uk/running-the-railway/our-routes/lnw/chase-line-electrification-rugeley-to-walsall/.

For travel information visit www.nationalrail.co.uk.    

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Network Rail press office - North West & Central Region
0330 854 0100
NWCmediarelations@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk