Revised plan means less passenger disruption on West Coast main line during essential Watford upgrade: West Coast main line blockade

Thursday 30 Jan 2014

Revised plan means less passenger disruption on West Coast main line during essential Watford upgrade

Region & Route:

Two proposed closures of the West Coast main line at Watford have been withdrawn after a detailed review of the work meant they were no longer necessary.

Network Rail had originally planned a 16-day closure in August 2014 and a nine-day closure in February 2015 to carry out significant upgrade work as part of an £81m investment to improve reliability and punctuality on one of the busiest sections of railway in Europe.

Following feedback from passengers and discussions with industry partners, a thorough review of the project has meant it has been possible to amend the planned work to be carried out over three weekends in August and two weekends in February, reducing the levels of disruption to passengers.

Dyan Crowther, Network Rail’s route managing director, said: “Working with our industry partners we have been able to develop a revised schedule of work at Watford that will cause less disruption for passengers.

“There is never a good time to close the railway and removing these two significant closures means we will have to carry out the work over eight separate weekends and Bank Holidays which will still impact on journeys. However, the feedback from passengers suggested this was a preferred situation.

“We will now liaise with the train companies to plan for the work and to provide passengers with information in advance and during the work to minimise disruption as possible.”

Phil Bearpark, operations and customer service director for Virgin Trains, said: “We welcome the news that Network Rail has created a plan that will not involve a 16-day closure in August or a nine-day closure in February, which would have had a significant impact on all our customers.

“Although the new plan now largely involves weekend and bank holiday closures, we are still aware that many customers will be affected and we are working with industry partners to offer sensible alternative travel routes.”

Patrick Verwer, London Midland’s managing director, said: “It’s great news that our colleagues at Network Rail have been able to revise the work schedule for the Watford resignalling project. Our passengers who commute into London on a daily basis were extremely concerned about the impact of the initial blockade dates, and I am confident they will welcome this decision”.

Guy Dangerfield from independent watchdog Passenger Focus said “Passengers will be enormously relieved that the West Coast route will not now be closed at Watford for days on end in August 2014 and February 2015”.

In the past 15 years the number of trains using the West Coast main line has doubled – increasing the pressure and wear and tear on the infrastructure. With the number of trains due to increase as Network Rail and train companies work together to increase capacity wherever possible, continued investment and renewals are essential to provide passengers with the best possible level of service.

During the work, all signalling between Kings Langley and Bushey will be renewed and more than 15km of new track will be laid. There will be an upgrade of the overhead line equipment and platform 10 at Watford Junction will be modified to allow longer trains to be stabled.

Notes to editors

The confirmed dates for work on the West Coast main line at Watford are:

2014:

Saturday 3 May to Monday 5 May (no change)

Saturday 9 August to Monday 11 August (revised)

Saturday 16 August to Monday 18 August (revised)

Saturday 23 August to Tuesday 26 August (revised)

Wednesday 24 December to Monday 29 December (no change)

2015:

Saturday 14 February to Monday 16 February (revised)

Saturday 21 February to Monday 23 February (revised)

Friday 3 April to Tuesday 7 April (no change)

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Network Rail press office - North West & Central Region
0330 854 0100
NWCmediarelations@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk