Railway through Bolton reopens: Moses Gate bridge repairs

Wednesday 6 Sep 2017

Railway through Bolton reopens

Region & Route:
| North West & Central

Passengers can travel by train between Bolton and Manchester again after the line reopened early following emergency repairs to a bridge which was badly damaged by a burst water main.

The Moses Gate railway bridge, near Bolton, was damaged on 17 August when the burst pipe caused a section of it to collapse onto the railway below and created a hole in the road above.

The line through the area fully reopened today (6 September) however, due to recent wet weather which has delayed some work, Moses Gate station will be closed until later in the week while work continues to complete upgrades as part of the electrification of the line.

Andy Morgan, senior sponsor for Network Rail, said: “This has been an extremely challenging repair programme and we have been working 24/7 to get passengers moving between Bolton and Manchester.  To repair the bridge, we have rebuilt a large section of wall which supports the bridge and make it stronger.  

“We have been working at Moses Gate station to make sure it is ready for electric trains to run.  However, due to the recent wet weather, it has slowed progress meaning the station will be temporarily closed until later in the week.

“I would like to thank all passengers for their patience during this complex situation.”

Liam Sumpter, Northern regional director, said:  “We look forward to welcoming customers back to Bolton from Wednesday as we restart our full train service for journeys into Manchester. 

“We want to thank all of our customers for their help and understanding over the last week.”

Before the water main burst, the railway through the area was already closed because of upgrade work at Bolton station as part of the Great North Rail Project. The station and railway between Bolton and Manchester was due to open on Monday 28 August. The work at the station – which included remodelling of the tracks, station platforms and signalling systems - was completed on time as planned and is part of plans to upgrade and electrify the railway to provide passengers with better, more reliable trains.

Although a completion date for work to the road is yet to be confirmed it is expected reopen within the original six week estimate.

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Network Rail press office - North West & Central Region
07740 782954
NWCmediarelations@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk