Tuesday 4 Mar 2014
Rail services to resume through Chesterfield area ahead of target
- Region & Route:
Rail passengers in the Sheffield and Chesterfield areas will be able to travel on their usual services from next weekend (Saturday 8 March) once engineers complete work to allow the line to re-open ahead of schedule.
Since Tuesday 18 February, trains have been disrupted with longer journey times and some cancellations after one of the two tracks near Unstone was closed. It followed the extremely wet weather which resulted in the hillside above the railway becoming unstable.
Initial estimates indicated that services would be disrupted for four to six weeks. However work on site has progressed better than expected, aided by an improvement in the weather. Network Rail will use a piece of kit called the high output ballast cleaner to carry out intensive work overnight on Friday 7 into Saturday 8 March to dig out the ground which has pushed the track up, refresh the ballast, and allow the track to reopen.
Phil Verster, Route Managing Director for Network Rail, said: “I thank passengers for their patience while we complete essential work to stabilise this hillside. It is a testament to the hard work of the team on site that we will be able to re-start a service from this Saturday.”
“The work completed so far has prioritised making the track safe so that trains can run but work to fully stabilise the hillside will continue for several months yet. Trains will run at a slightly reduced speed past the worksite but this will not significantly affect journey times.”
Engineers are confident the work to stabilise the hill side can be completed without further changes to the timetable. The track which will be treated by the high output ballast cleaner will be carefully monitored. If any follow- up work is required, Network Rail will notify customers in advance and schedule the work to minimise disruption.
CrossCountry, East Midlands Trains and Northern Rail said: “We would like to thank customers for their patience and understanding during this disruption. We have been working closely with Network Rail to get the line re-opened and are pleased this has been achieved ahead of their original estimate."
Contact information
Passengers / community members
Network Rail national helpline
03457 11 41 41
Latest travel advice
Please visit National Rail Enquiries
Journalists
Network Rail press office -London North Eastern & East Midlands route
01904 383180
mediarelations@networkrail.co.uk
About Network Rail
We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.
Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.
Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk