RAIL SERVICES RESUME AS VIADUCT REOPENS: Road/rail vehicle working in conjunction with gantry cranes

Monday 18 Jul 2011

RAIL SERVICES RESUME AS VIADUCT REOPENS

Region & Route:

Project delivered on time and under budget

Embedded image 

Arnside Viaduct reopened on schedule this morning (18 July) after a 16-week closure during which Network Rail and its principal contractor May Gurney completely rebuilt the deck of the 155 year old structure.

Jo Kaye, Network Rail’s route director, said passengers are now reaping the benefits of the work. “The first thing regular passengers will notice is how quiet the ride is over the viaduct compared with before. We have taken away the old jointed track and replaced it with continuous rails. Not only is this quieter but it is also makes the ride over the viaduct a lot smoother.

“In due course we will be doubling the speed of trains over the viaduct which could lead to reduced journey times in future timetables.”

Arnside Parish Council expressed its appreciation for the way the work had been carried out, saying: “It has been on time with a minimum of mess and disruption to the village, for which we are grateful.”

Site compounds were set up at either end of the viaduct, which closed at the end of March. Old material was taken away in the Grange direction and the new decks brought in from the Arnside compound.

Working on one line at a time, the railway tracks were removed to expose the viaduct decks, which were cut into sections, lifted out by special road/rail machines and taken away to the Grange compound.

Special gantry cranes were then erected which moved along the viaduct lifting the new deck units into position before base plates were bolted in place to take the new continuously welded track. The type of base plates and track used mean a quieter, smoother ride for passengers and less maintenance for both Network Rail and train operators.

Having completed the line towards Barrow, the process was reversed to renew the viaduct in the Carnforth and Lancaster direction.

The 30 mph speed restriction is due to be removed after a settling in period, and the speed of trains over the viaduct is expected to be increased to 60 mph in the New Year.

Notes to editors

  • The original budget for the project was £12m but efficiencies drove the final cost down to £10.7m

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Network Rail press office - North West & Central Region
0330 854 0100
NWCmediarelations@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk