Key Carlisle rail routes reopen for passengers after freight derailment: Northern train passing over repaired Petteril Bridge junction with B&Q in background

Wednesday 7 Dec 2022

Key Carlisle rail routes reopen for passengers after freight derailment

Region & Route:
North West & Central

Rail passengers are being thanked for their patience after a freight train derailment cut off two key rail routes in Carlisle for seven weeks.

Since 6.00am this morning (Wednesday 7 December) direct trains are now running again on the Tyne Valley line between Carlisle and Newcastle and the Settle to Carlisle line between Carlisle, Appleby and Skipton.

Network Rail engineers have been working around the clock to restore the railway at Petteril Bridge junction after a train carrying powdered cement left tracks on Wednesday 19 October.

Huge damage was caused to a Victorian-built railway bridge, railway lines and signalling equipment during the incident.

More than 25,000 hours of work has taken place to get the railway restored so trains can run again.

Drone footage has been released today (Wednesday 7 December) showing some of the first passenger trains to pass over the new tracks and strengthened bridge.

Mark Evans, Network Rail senior programme manager, said: “I’d like to thank passengers for their patience while we worked tirelessly to get the railway back up and running after it was severely damaged by the freight train derailment.

“This has been a very complex recovery and repair job. Now it’s complete this major railway junction is future-proofed and has been strengthened in the very rare event anything like this should happen again meaning more reliable journeys for passengers and freight for years to come.”

Kerry Peters, regional director at Northern, said: “We have been working very hard with Network Rail to reopen the railway at Petteril bridge following the freight train derailment in October.

“Now that work is complete, Northern services have resumed on both the Tyne Valley and Settle to Carlisle lines – and we have allocated extra advance purchase fares to welcome people back on-board. We’d like to thank our customers for being patient during this disruption and everyone involved in getting our passengers moving again.”

Over the last seven weeks:

  • Forensic rail accident investigators assessed the cause of the derailment
  • The locomotive and 11 of 14 wagons carrying powdered cement were recovered soon after the incident
  • Giant vacuums removed 80 tonnes of powdered cement from 3 wagons which needed lifting
  • Environment Agency experts made sure no contamination entered the river Petteril
  • An 800-tonne crane recovered those wagons which ended up in the water and on the embankment
  • Eighty metres of damage track was replaced
  • 400 metres of cabling was installed for signals and points
  • Replacement of two switches – moving sections of track which enables trains to switch lines
  • 125 tonnes of structural concrete was poured into 16 tonnes of metal reinforcement cages to repair the damaged railway bridge over the river
  • The work took 25,000 hours, over 40 people working 7 days-week, for 7 weeks.

Passengers are being advised to check before they travel if planning journeys over the festive season by visiting www.nationalrail.co.uk for the latest information.

Notes to Editors

*The derailment involved one locomotive hauling 14 wagons, each filled with 80 tonnes of powdered cement, as it travelled between Clitheroe and Carlisle on Wednesday 19 October.

Five of the wagons derailed shortly after 8pm at Petteril Bridge Junction.

An initial report published by the Rail Accident Investigation Branch found that a fault with a train wheel was the most likely cause of the derailment.

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Network Rail press office - North West & Central Region
0330 854 0100
NWCmediarelations@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk