No crane no gain: Network Rail install first part of new fully accessible footbridge at Llanhilleth station: Llanhilleth footbridge crane lift hero

Thursday 6 Apr 2023

No crane no gain: Network Rail install first part of new fully accessible footbridge at Llanhilleth station

Region & Route:
Wales & Western: Wales & Borders

Engineers from Network Rail and contractors, AmcoGiffen, completed lifting a fifteen-piece footbridge using a mobile 230-tonne-crane at Llanhilleth, South Wales, last week.  

The five-day closure of the line, from 25 to 30 March, saw a team of 13 engineers guiding the near 65-tonne-footbridge onto its new foundations across the Ebbw Vale line.  

As part of the Ebbw Vale enhancement scheme that will see an increase in service from Newport to Ebbw Vale town, the crane lifts took only a day-and-a-half in some very wet weather conditions to complete.  

The footbridge, manufactured away from site, was installed section-by-section and consisted of eight columns, six sections of stairs and the 17.9 metre-long-bridge span that weighed 15.5 tonnes.  

The line is due to close again at the end of April (23-30 April) so teams from Network Rail and AmcoGiffen can install two new lifts, making the bridge fully accessible. Local residents and passengers will be able to easily get across the railway once the footbridge opens later in the summer.  

Thomas Edwards, project manager at Network Rail said: “It’s great to see this brand new fully accessible footbridge come together.  

“We know how important it is to make the railway accessible for everyone and we would like to thank local residents and passengers for their understanding of the need to close the railway to make it happen.”  

Matthew Richards, project manager at AmcoGiffen, added: “Despite some horrendous wet weather, we were lucky with the wind as the gusts weren’t too strong and were able to complete the lift in good time.  

“It’s very pleasing to see the bridge installation take place. This is a combined effort, and we would like to thank all involved for the hard work put in over the past few months to get us to this point.”  

Notes to Editors

This £70m project has been funded by Blaenau Gwent County Borough Council via a loan from the Welsh Government. The Department for Transport and Network Rail are providing a further £17m of funding to deliver the signalling upgrade and renewal work.  

Work will continue across the whole Ebbw Vale Line until late Summer 2023. Further line closures will be needed to carry out the work safely:   

  • Sunday 21 May  
  • Wednesday 24 May to Sunday 11 June (inclusive)  
  • Sunday 18 June   
  • Sunday 25 June   
  • Sunday 2 July   
  • Sunday 9 July   
  • Sunday 16 July   

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Callum Jones
callum.jones2@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk