Monday 21 Jan 2013

Network Rail holds information centres for West Coast works

Region & Route:

Network Rail is holding a series of ‘drop-in’ information sessions in Staffordshire in support of a proposed programme of improvement works in the Norton Bridge and Stafford area.

Submitted to the Planning Inspectorate, the application plans and documents relating to the improvements are available for public viewing.

In 2011 a preferred scheme was announced which included plans for a new flyover at Norton Bridge to remove a major ‘bottleneck’ on the West Coast Main Line (WCML) to provide a more reliable, efficient and cost effective railway.

The proposed new section of track (incorporating the flyover) will be approximately 6.8 km in length and will run from Little Bridgeford in the south, passing to the west of the WCML and Norton Bridge, before rising to cross over the WCML and reconnect with the Stone/Manchester branch line. In addition, a single railway track will reconnect the north bound slow railway line to the WCML north of Norton Bridge.

On completion, the investment will deliver:

  • Two extra fast trains per hour in each direction between London and the North West
  • One extra train per hour in each direction between Manchester (via Stone) and Birmingham
  • One extra freight train per hour in each direction through Stafford

Network Rail has already held four separate rounds of public consultation regarding the improvements with the local community, which has helped to shape the scheme. An application to construct the new flyover was also submitted to the Planning Inspectorate for consideration in December 2012. That application has now been accepted for examination by the Planning Inspectorate and will be examined by an Inspector during 2013..

The application documents are available to view at Stafford Borough Council and Eccleshall library and also electronically on the Network Rail website at www.networkrail.co.uk/Stafford-NortonBridge and on the Planning Inspectorate website at http://infrastructure.planningportal.gov.uk/projects/west-midlands/stafford-area-improvements-norton-bridge-railway/ . In addition, a series of informal ‘drop-in’ sessions where members of the project team will be available to answer any queries will be held on the following dates:

  • Tuesday 29 January 2013 (2pm-4pm) Stafford Borough Council
  • Thursday 31 January 2013 (3pm-5pm) Eccleshall Library
  • Wednesday 6 February 2013 (10am-12pm) Stafford Borough Council
  • Saturday 9 February 2013 (10am-12pm) Eccleshall Library
  • Wednesday 13 February 2013 (2pm-4pm) Stafford Borough Council
  • Friday 15 February 2013 (9am-11am) Eccleshall Library

Should you have any queries regarding the Stafford/Norton Bridge proposals you can:

Notes to editors

Birmingham to Manchester trains leave the main line at Norton Bridge to continue their journeys to Stoke, Macclesfield, Stockport and then Manchester. While they cross this busy junction, trains travelling to and from destinations such as Liverpool, Preston, the Lake District, Carlisle and Scotland cannot pass through the Norton Bridge area. This reduces train speeds and has the potential to cause delays that can have a knock-on effect in other parts of the network.

Details of the consultation and a summary of the option selection assessment can be viewed online at www.networkrail.co.uk/Stafford-NortonBridge

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Network Rail press office - North West & Central Region
0330 854 0100
NWCmediarelations@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk