Major refurbishment to key York rail bridge gets underway: Scarborough Bridge, York

Monday 3 Nov 2014

Major refurbishment to key York rail bridge gets underway

Region & Route:

The most significant work to the Scarborough rail bridge in York for 140 years will start in November.

The £6m investment is the most significant since the bridge was built in 1875 and, once complete, will mean that the bridge is fit for another 120 years’ service. Work will involve replacing bridge decks, track and installing a new walkway to improve safety for railway workers.

The site compound will be set up in Marygate car park from November. The project is due to complete in March 2015.

Phil Verster, Route Managing Director for Network Rail, said: “The Scarborough Bridge has given good service for 140 years but is now due for refurbishment. Once these improvements are complete, many parts of the bridge will not need any further work for decades. We will have people working on site every day to get this work finished.

“This is a complex project as the bridge spans the River Ouse and is in the middle of a residential area with narrow streets as well as being close to several important rail lines. We have worked very closely with the City of York Council and First TransPennine Express to minimise the impact of the work on both local residents and the travelling public. I thank them for their patience while we undertake these essential works.”

When the bridge’s decks are replaced in February 2015, trains will not be able to run over the bridge. The new decks will be installed from Marygate car park using a large crawler crane.

This is being carefully managed between Network Rail and First TransPennine Express, and buses will replace trains between York and Scarborough from 14 to 22 February 2015; during the school half-term holidays. More detailed information will be issued over the coming weeks.

Anna-Jane Hunter, from First TransPennine Express, said: “We are working with Network Rail to minimise the disruption caused by the improvement works and put in place the best possible journey options for customers.

"Express coaches will replace rail services between York and Scarborough and we will shortly be issuing updated timetables and customer information posters.

"We would advise customers to check before they travel and allow extra time to complete their journey. Full details of the improvements works and alternative arrangements will be available from National Rail Enquiries."

As part of the work, it will be necessary to remove some trees and vegetation from the railway embankment immediately north east of the bridge, but these will be replaced with a replanting scheme after the work finishes in the spring of 2015. A full ecological study has been carried out.

Network Rail has planned this work closely with the Canal and Rivers Trust, Natural England and Environment Agency, securing the necessary permissions. This is because the River Ouse will need to be closed to river traffic for certain times while the works are undertaken.

The footpath under the bridge and footbridge which is attached to the rail bridge will need to be closed at various times next February for safety purposes. This will be kept to a minimum.

Network Rail’s 24-hour, helpline is available for anyone to report any issues with the rail infrastructures on 08457 11 41 41.

Notes to editors

Scarborough bridge was originally built in 1845, and was rebuilt in 1875

This is the first reconstruction of Scarborough Bridge for more than 140 years. The bridge is life-expired and needs to be replaced.

Once completed the bridge deck:

  • Won’t have to be replaced for 120 years
  • Won’t need painting for 25 years
  • Will have improved track drainage
  • Will have a safe walking route for our engineers to use

The work will mean that the bridge is capable of carrying heavy steam services, such as the Flying Scotsman

Half term is quietest period for FTPE which is why the removal and replacement of the deck has been scheduled for then

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Network Rail press office -London North Eastern & East Midlands route
01904 383180
mediarelations@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk