£76m signal and track upgrade completed on time as Network Rail reopens railway between Banbury, Bicester and Leamington

Region & Route:
| North West & Central

The railway line between Banbury, Bicester and Leamington Spa reopened today after Network Rail completed a £76m upgrade to track and signalling on the Chiltern main line.

Engineers have replaced the signalling through Banbury by upgrading it to a more reliable and modern system which will be controlled from the West Midlands Signalling Centre in Birmingham. 

The work by Network Rail, part of the Railway Upgrade Plan, will help improve the punctuality and reliability of train services on the Chiltern main line, providing Chiltern Railways passengers with a better railway between Birmingham and London and CrossCountry passengers with a better railway through the area.

As part of the railway upgrade at Banbury 14,000 metres of new rail has been laid and 50,000 tonnes of ballast – the stone which forms the foundation of the track – has been used. A total of 24 new points – which allow trains to change from one track to another – has been installed.

Much of the work had already taken place prior to the nine-day closure between Leamington, Bicester North and Banbury, keeping disruption to passengers to an absolute minimum.

In addition to the new track layout through Banbury station and the modern signalling being installed, a new fourth platform was constructed allowing for greater capacity and flexibility at the station. The investment also provides the necessary infrastructure for a new depot south of Banbury which is currently being built. This will provide essential maintenance provision for the growing Chiltern Railways train fleet. 

Martin Ball, area director for Network Rail, said: “This work was completed on time and with the least amount of disruption to passengers and is an important part of modernising the railway through the area to provide passengers with a more reliable, better railway. 

“Our engineers worked quickly and safely to complete this work on time and on budget and we worked closely with the train operators involved to carefully plan these improvements to cause the least amount of disruption to passengers. I’d like to thank passengers for their patience while the improvements took place.

“Our Railway Upgrade Plan is delivering significant investment into the railway network which will provide a better, more reliable railway for passengers.” 

Dave Penney, managing director at Chiltern Railways said: “The work at Banbury was an essential investment in the long term reliability of the railway and was successfully delivered on time.  Through a modernisation of the signalling system,  Chiltern Railways services can remain some of the most punctual in the country.  The 18 month project is now complete and I would like to thank all of our customers who have shown patience and understanding during the improvements, particularly during the recent nine day line closure between Leamington Spa and Bicester.” 

Andy Cooper, managing director of CrossCountry, said: “We are delighted this important work was finished as planned and that our customers are once again able to complete their journeys by train. We would like to thank everyone affected for their patience while this was taking place, and know that this investment in a bigger and better railway will benefit our customers for years to come.”

For more information about this project, please visit www.chilternrailways.co.uk/banbury-upgrade.

Work at Hinksey, near Oxford is also progressing well where engineers are working to reduce flooding incidents which have affected the railway in the past. 

A total of £18m is being spent to make the railway more resilient which will mean services between Oxford and Didcot Parkway will also be affected between until Sunday, 14 August. 

Passengers are advised to check before they travel at www.nationalrail.co.uk for the latest information. 

ENDS 

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Network Rail press office - North West & Central Region
07740 782954
NWCmediarelations@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk