Further reliability boost for rail services between Newport and Gloucester as Network Rail completes second phase of multi-million-pound resilience scheme: SERP phase two HERO

Friday 18 Aug 2023

Further reliability boost for rail services between Newport and Gloucester as Network Rail completes second phase of multi-million-pound resilience scheme

Region & Route:
Wales & Western: Wales & Borders

The Severn Estuary line has today (Friday 18 August) reopened after three weeks of 24/7 work to mitigate the impact of weather-related landslips that will improve train performance, reduce delays, and ensure the highest level of reliability for passengers and freight services. 

More than 100 engineers from Network Rail and principal contractor, AmcoGiffen, along with their strategic partner QTS Group, worked around the clock, from Monday 31 July to Friday 18 August, to install an ‘active’ mesh system on the cliffs overlooking the exposed railway between Monmouthshire and Gloucestershire. 

The teams worked more than 34,000 hours, with trained specialist rope access technicians abseiling down the cliff face, removing 1,000 tonnes of loose material before securing the specially designed netting with 5,000 rock bolts.  

This bespoke ‘active’ system will hold the cliff face in position and help to prevent landslips from damaging, and subsequently, closing the railway.  

Watch Phase Two of the scheme below:  

Part of a wider multi-million-pound investment, this work demonstrates Network Rail’s commitment to boosting resilience and mitigating the impacts of climate change on the Wales and Borders route.  

This section of railway was hit by three landslips in January 2023 alone, following a bout of prolonged heavy rainfall, which has led to a huge financial and disruptive impact. 

To safely run trains following the recent landslips, Network Rail imposed a temporary speed restriction (TSR) of 20mph – reduced from the normal line speed of 75mph. This has caused nearly 6,000 delay minutes, costing more than £400,000 of taxpayers’ money.  

The completion of this next phase means the TSR can now be removed, improving journey times and reducing costs to the taxpayer.  

Phase One of this project was completed last summer and has also had huge benefits.  

Nick Millington, route director for Network Rail Wales & Borders, said: “We are dedicated to improving resilience across the Wales & Borders route and we’re already seeing the benefit this multi-million-pound investment is having on the Severn Estuary line. The new mesh installed on a different section of the cliff, last Summer, has had zero landslips that have impacted the railway.  

“With Phase Two now complete, the whole line is better protected against severe weather events. We will be coming back to carry out more resilience work to further future proof this line against the challenging effects of climate change.  

“I would like to thank passengers and the local community for their patience while we carried out these vital improvements.” 

Andy Crowley, operation director for Wales & Borders at AmcoGiffen, commented: “We know how important our rail infrastructure is to passengers and freight and we’re delighted to have safely and successfully achieved our targets during this blockade.  

“Working diligently alongside our sister company QTS Group, we’ve completed this crucial phase of the essential Severn Estuary Resilience Programme with the cutting slope stabilisation, handing back the blockade on time, as planned. 

“This project showcases our commitment to collaboration, excellence and innovation to ensure journey efficiency and reliability for customers with a minimum impact for our lineside neighbours.” 

Gary Burnett, Operations Director for QTS, added: “The effort that our team has put into ensuring the success of these works at the Severn Estuary is something to be proud of. 

“Being able to utilise the very best in rail plant innovation has allowed us to deliver these works on time, and as efficiently as possible, working in partnership with AmcoGiffen for Network Rail. 

“We are pleased to have managed to carry out these works with minimal disruption for our lineside neighbours and thank them for their patience during the period of works.” 

Network Rail and contractors will remain on site on the Severn Estuary to install more bolts and mesh until March 2024. This work will not be disruptive to rail services.  

Designs and plans for the next stage of this resilience project are currently being finalised, with teams expected to return next year to upgrade Phase One’s ‘passive’ system - that catches debris rather than holds it in place - with an ‘active’ system.  

Notes to Editors

As well as specialist rope access, the QTS team also utilised its innovative fleet of road rail machinery. This included the QTS Mega Reach, the largest RRV lorry loading crane working on the UK rail infrastructure, which features a full crane extension of up to 29m.  

For this project, the Mega Reach was fitted with a specialised drill rig and extended to a reach of 20m, allowing it to drill to the top of the cutting slope from track level. This removed the requirement for hand drilling by the operatives and creates a safer, more efficient way of working.  

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Callum Jones
callum.jones2@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk