First steps towards the Chase Line’s electric future: Broad Lane bridge, Bloxwich

Thursday 26 Sep 2013

First steps towards the Chase Line’s electric future

Region & Route:

Electric trains on the Chase Line will move a step closer this Autumn as Network Rail starts work to electrify the railway between Walsall, Cannock and Rugeley Trent Valley.

The project will see 15 miles of railway electrified to connect to existing electric railway at Walsall and Rugeley and provide a better service for passengers using the route.

Liam Sumpter, Network Rail area director said: “Electrification helps us to boost capacity, reduce carbon emissions and cut the cost of running the railway. Electric trains are also quieter, more reliable and have more seats, which is good news for passengers.

“By enabling a better train service along this important route, we can provide the railway that Chase Line passengers want and the areas economy needs.”

This Autumn, Network Rail is starting work to rebuild 3 bridges in Walsall and Hednesford to accommodate the equipment needed to run electric trains. During the rebuilding of each bridge, local roads across Broad Lane and Station Road bridge will be closed* with diversions in place to allow the project to be completed safely.

Network Rail has been working closely with local authorities to agree the details of the closures and inform local residents. The project team will be holding a series of ‘drop in’ information sessions where people can find out more about the project and how it will affect them:

Friday 27 September 1300-1800, Bloxwich Library

Wednesday 2 October 1100-1900, Cannock Chase Civic Centre

Thursday 3 October 1100-1900, Rugeley Leisure Centre

Friday 4 October 1100-1900, The Council House Walsall

Once all bridge works have been completed, electrification work will get underway in 2015 with the project set for completion in late 2017.

Rail services will not be affected until spring 2014 when the line will be closed for short periods on Sunday mornings to allow construction work to be completed safely. London Midland will provide a rail replacement service during these periods.

*One lane of Walkers Rise bridge will remain open throughout the rebuild and temporary footbridges will be installed at Broad Lane and Station Road bridges.

Notes to editors

Rail services will not be affected until spring 2014 when the line will close on a series of Sunday mornings between 07:30 and 12:30 to allow construction work to be completed safely:
16 & 23 February 2014
2, 8, 16, 23 March 2014.
London Midland will provide a rail replacement service during these periods.

All 3 bridges are brick arch structures and need to be rebuilt to accommodate the overhead line equipment that will be used to electrify the Chase Line:

Broad Lane bridge (Bloxwich):

Start of work on site: October 2013

Road closure: 11 November 2013 to 31 March 2014 - pedestrian access will be maintained across the bridge apart from 24-27 December 2013 when the main bridge reconstruction will take place.

Bridge rebuild complete: April 2014

Station Road bridge (Hednesford):

Start of work on site: January 2014

Road closure: January – April 2014 - Network Rail will reconstruct the existing pedestrian footbridge structure in advance of this work so that pedestrian access is maintained.

Main reconstruction work to take place during a series of 12 hour closures of the railway line in February/March 2014.

Bridge rebuild complete: April 2014

Walkers Rise bridge (Hednesford):

Start of work on site: January 2014

After consultation with local businesses and councillors, one lane will remain open on this bridge throughout the project to maintain access into the Cannock Enterprise Centre

Main works to be undertaken during a series of 12 hour closures of the railway line in February/March 2014.

Bridge rebuild complete: April 2014

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Network Rail press office - North West & Central Region
0330 854 0100
NWCmediarelations@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk