Final repairs underway to damaged wall overlooking Liverpool Lime Street tunnels: Aerial shot of the collapsed wall as seen from Network Rail's helicopter

Tuesday 25 Jun 2019

Final repairs underway to damaged wall overlooking Liverpool Lime Street tunnels

Region & Route:
North West & Central

Permanent repairs have begun on a retaining wall which collapsed onto the railway at Liverpool Lime Street station causing major disruption two years ago.

Two hundred tonnes of debris fell onto the track in February 2017 when the wall was overloaded with concrete and temporary buildings on land next to the railway owned by Liverpool City Council.

Overhead electric lines, track and essential railway equipment was damaged.

It forced the station to close with no trains able to run in or out of Lime Street for a week.

A temporary repair was made to quickly get the station open again in 2017, but now final structural repairs are underway.

Tony Duncan, Network Rail project manager, said: “I’m pleased our team are able to complete the final repairs to the retaining wall above Lime Street tunnels.

“The collapse of the wall two years ago halted trains in and out of the station for several days and caused severe damage to our tracks and equipment.

“I’d like to thank Liverpool City Council for working with us to help complete this vital work.”

Network Rail is due to complete the wall repairs by autumn 2019, without any disruption to trains or passengers.

The land next to the railway is being redeveloped by Liverpool City Council into a new energy centre.

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Chris Halpin
0330 8540100
chris.halpin@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk