Friday 1 Apr 2011

FASTER TRAINS AND MORE SERVICES FOR YORK STATION – WITH MINIMAL TRAVEL DISRUPTION

Region & Route:

Rail passengers in York will have faster and easier journeys after a new track layout is installed at the south end of the station, meaning they will not have to wait on trains to get into a platform.

Work on site at Holgate, south of York, begins this month to provide an additional line and new junction. It is part of a multi-million programme of improvements which will allow faster services and more trains to run on the east coast main line (ECML).

Where once this would have resulted in lengthy delays and cancellations to rail services; close working with train operators has allowed Network Rail to develop a plan which sees few changes to the timetable.

Richard Lungmuss, route director for Network Rail, said: “This is the most significant single investment in the railway in this area since electrification. At the moment trains heading from Leeds to the north east and Scotland conflict with other passenger services, often resulting in trains being forced to stand before they can access a platform. This has been a frustrating bottleneck for many years and this scheme will bring direct benefits to many thousands of passengers as well as being a key part of wider investment to improve the ECML.

”The vast majority of rail services will be unchanged during the works, minimising disruption to passengers while we deliver this value-for-money scheme which will bring real benefits rail users around York.”

Engineers from Network Rail have completed ground investigations and compounds will be set up from the start of April 2011.

Construction work will begin in April but the first significant site works will be in early May.

There will be some small changes to rail services from 30 July for 12 weeks

On August bank holiday weekend there be significant changes to services while new track layout is installed and some electrification work is carried out. These changes will be publicised in advance.

The investment at Holgate is worth approximately £9.5m

Notes to editors

The Holgate project is part of a package of works scheduled between 2009 and 2014 to improve capacity and reliability of services on the ECML. In all the investment in the line is worth approximately £600m.

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Network Rail press office -London North Eastern & East Midlands route
01904 383180
mediarelations@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail