Network Rail sets out plans to fully re-open the Newcastle to Carlisle line: Aerial image of Farnley Haugh landslip 1

Thursday 14 Jan 2016

Network Rail sets out plans to fully re-open the Newcastle to Carlisle line

Region & Route:
  • Newly released aerial photos reveal scale of the problem
  • Team is working with Historic England to protect Roman remains in fields above the railway

Engineers working to repair a landslip near Corbridge on the line between Newcastle and Carlisle say they plan to re-open the line in three to four weeks as long as their work is not further affected by the weather.

25,000 tonnes of earth need to be removed from the site at Farnely Haugh after exceptional rainfall caused drainage to become overwhelmed, leading to the landslip.

Network Rail route managing director, Rob McIntosh, today visited site to see the progress of work to restore train services.  Commenting on the disruption being caused to passengers he said, “I want to thank passengers for their patience while we complete this delicate repair. The north of England has taken a battering from the weather.  In the main we have been able to keep trains running and make sure passengers are able to complete their journeys.  Unfortunately this landslip means the line between Prudhoe and Hexham will be blocked for another three or four weeks.

“The team had to divert the water which was feeding the slip and make sure it had stopped moving before they could start work.  They have also been liaising with Historic England to protect the three Roman forts and possible Roman road which are buried in the fields above the landslip.  This week they have removed the trees from the slope and are making preparations to begin the job of carefully removing the slipped earth and shoring up the cutting to prevent it from moving again in the future.

“We know how disruptive this is for passengers and are working as quickly as we can without compromising safety on site.  If there is any opportunity to restore train services sooner then we will do so.  We will work with Northern Rail and other local stakeholders to make sure passengers have the best information available to help them to plan their journey.”

25,000 tonnes of material needs to be excavated and removed from site to repair the landslip. Engineers plan to remove the vast majority of this by rail which will allow 200 tonnes per hour to be removed from site. 

Information about train services can be found via National Rail Enquiries and Northern Rail.  For the latest timetable information, please visit for the latest timetable information: northernrail.org/tynevalley.

Real time journey information can be found at journeycheck.com/northernrail or by Tweeting their team: @northernrailorg.

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Network Rail press office - Rachel Lowe
Network Rail
rachel.lowe@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk