Friday 4 Mar 2011
ELECTRIFICATION WORK PICKS UP SPEED
- Region & Route:
Network Rail has been pressing ahead with ‘behind the scenes’ work to electrify the Manchester to Liverpool railway line since the announcement by the Department for Transport last year.
A detailed study of every structure along the route has been undertaken to see what needs to be done to accommodate the 25,000 volt overhead cables that will provide electricity to drive the trains.
Jo Kaye, Network Rail’s route director, explained: “We have looked at all the tunnels and road and pedestrian bridges along the entire route, many of which are up to 150 years old. Some will need work to be carried out on them before the overhead power lines can be put in place.
“Having done all the background work we are now at the stage where we are ready to start on the ground.”
Two road bridges and one pedestrian bridge over the railway between Eccles and Patricroft stations are to be demolished and rebuilt. They are Albert Street, Old Wellington Road and Chadwick’s footbridge.
Albert Street will close from 15 March for up to 20 weeks and a signed diversionary route will be in place. During the closures, pedestrian access over the railway will be maintained for the majority of the time.
At the same time, Old Wellington Road will be restricted to single lane traffic, again for up to 20 weeks.
However, there will be three consecutive weekends in June when both bridges will have to be closed to vehicles and pedestrians.
Chadwick’s footbridge will be completely closed from mid-May until the end of June and an alternative pedestrian route will be provided.
In total, there are 90 structures on the route, 46 of which will not need any work. This is either because there is already sufficient headroom or because the cables can be installed in such a way as to not need any work. However 44 will need some attention. In some instances, this will mean the bridge can simply be raised up, some will have to be rebuilt and in other locations the track can be lowered, leaving the bridge unaffected. Some bridges will only require work to their parapets.
There is also one short tunnel on the line between Patricroft and Newton-le-Willows through which the track will be lowered.
A well as looking at the various structures, Network Rail has also been looking at the effect the work will have on the signalling along the line, particularly where bridges are rebuilt or the track is lowered. This is so that signals are not obscured from the train driver’s view.
Notes to editors
- The Liverpool to Manchester line is 30 miles long
- The section to be electrified runs from Manchester Victoria to Edge Hill (Liverpool) where it joins the main line into Lime Street station
- It also includes the section from Ordsall Lane Junction (Salford) to Castlefield Junction (Deansgate station), thereby providing a link to Manchester Piccadilly and the west coast main line; and the section from Parkside Junction to Golborne Junction and Winwick Junction to Earlestown West Junction, providing further links to the west coast main line.
Timescales
- The section from Manchester to Newton-le-Willows is due to be electrified in 2013
- In parallel with the Liverpool – Manchester electrification project, work is also under way on three further electrification schemes in the north west, namely
- The remainder of the Manchester to Liverpool line, plus Huyton to Wigan – due for completion in 2014
- Blackpool to Preston – due for completion in 2015
- Manchester to Euxton Junction (Chorley) – due for completion in 2016
Contact information
Passengers / community members
Network Rail national helpline
03457 11 41 41
Latest travel advice
Please visit National Rail Enquiries
Journalists
Network Rail press office - North West & Central Region
0330 854 0100
NWCmediarelations@networkrail.co.uk
About Network Rail
We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.
Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.
Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk