Saturday 29 Mar 2025
COMPLETED: Staines to Windsor line reopens after essential railway upgrades
- Region & Route:
- Southern: Wessex
Train services between Staines and Windsor & Eton Riverside resumed running this morning (Saturday 29 March) following a week-long closure to carry out vital railway upgrades.
During the past week, Network Rail’s team of engineers has laid over 700m of new track, including over the 174-year-old Black Potts Railway Bridge which crosses the River Thames, just a mile away from Windsor Castle. The new rail is welded together to ensure smoother and more reliable journeys for passengers between Staines and Windsor.
Part of the railway through the Windsor area has a sharp curve which places additional stress on the steel rails that the trains travel on. To bolster the longevity of this section of track, engineers installed lateral supports to the sleepers which will bolster the strength and durability of the rails through this curve.
During this time, engineers also completed a range of other work in the wider Staines-upon-Thames area, including:
- Track upgrades and maintenance on the line between Staines and Egham and from Staines to Ascot and Woking.
- Structural repairs to the bridge over the River Wey near Addlestone.
- Installing new sleepers in the Feltham area.
- Widening the pedestrian walkway on one side of Mays Level Crossing by Datchet station.
- Cutting back overgrown trees and shrubs to maintain the safety of the railway on the Windsor line.
Mark Goodall, Network Rail’s Wessex Route Director, said: “I’d like to thank passengers for their patience over the last week while we carried out this essential maintenance work in the Windsor area.
“This week-long closure has allowed us to carry out a complex re-railing job over Black Potts Railway Bridge amongst a number of other important jobs and will ensure the continued safe and reliable running of services on the Windsor line for years to come.”
Peter Williams, Customer and Commercial Director for South Western Railway: “We are very pleased to see the line between Staines and Windsor & Eton Riverside reopen following this essential maintenance work. We are very grateful for our customers’ patience and look forward to welcoming them back on our services.”
Notes to Editors
B-Roll from the engineering works can be downloaded by clicking here
Contact information
Passengers / community members
Network Rail national helpline
03457 11 41 41
Latest travel advice
Please visit National Rail Enquiries
Journalists
Tom Moore
Communications Manager
Network Rail
07354531500
Thomas.Moore@networkrail.co.uk
About Network Rail
We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.
Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.
Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk