Barmouth Viaduct reopens to rail passengers and pedestrians as second stage of major refurbishment work completes: Barmouth - credit Dom Vacher Dec 2022-3.jpg

Friday 9 Dec 2022

Barmouth Viaduct reopens to rail passengers and pedestrians as second stage of major refurbishment work completes

Region & Route:
Wales & Western: Wales & Borders

The railway and footbridge across the Grade II* listed bridge will reopen on Saturday 10 December, as Network Rail prepares for final metallic upgrades in 2023. 

Network Rail and contractors Alun Griffiths have successfully carried out a number of essential upgrades to Barmouth Viaduct in 2022 as part of the structures biggest and most ambitious refurbishment, ever.  

During two four-week closures this autumn and winter, teams have worked day and night to strengthen and replace timber beans, foundation support structures (piles), and the metallic straps that help hold the viaduct together.  

The closure of the railway allowed Network Rail to also upgrade a kilometre of track through the nearby Tywyn station. Barmouth Station’s canopy was also refurbished. 

The work was scheduled to take place outside of the peak summer tourist season to minimise disruption to the local community, with the viaduct reopening during October half term.  

The viaduct will reopen with a normal train service on Saturday 10 December so local communities and tourists can fully enjoy the spectacular wooden structure and its surrounding natural beauty this festive period.  

Nick Millington, interim route director at Network Rail Wales and Borders, said: "We’d like to thank the local community for bearing with us this autumn and winter as we carried out the latest stage of this essential restoration project.  

“We’ll be returning in 2023 to replace the metallic elements of the bridge, which will secure the future of this important rail link for many years to come.” 

Notes to Editors

  • Dates for working on the viaduct during 2023 are still being finalised.     
  • The work to refurbish the iconic railway structure is the biggest and most ambitious in its history. As well as upgrading the metallic elements of the Grade II* listed bridge and laying new track, additional repairs will be carried out including strengthening work to the north abutments and further upgrades of some of the timber elements following the major renewals of timber in 2020 and 2021.     

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Callum Jones
callum.jones2@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.