Abseil teams tackle steep conditions to protect railway cutting from rockfalls: Arley cutting strengthening work main view

Tuesday 21 May 2019

Abseil teams tackle steep conditions to protect railway cutting from rockfalls

Region & Route:
North West & Central

Specialist abseiling teams are protecting a section of Victorian-built railway in Warwickshire to prevent delays caused by rockfalls.

Network Rail is investing £6m as part of Britain’s Railway Upgrade Plan to secure a steep railway cutting at Arley near Nuneaton on a section of line which links the West Midlands to Leicester.

The permanent fix will stop the need for costly temporary repairs and will ensure the reliability of the key route for passenger trains and freight customers.

Although the area is hilly it is not the natural landscape - it was in fact shaped by the man-made leftovers from coal mining before the railway was built in the 1840s.

Above the cutting to the east of Arley Tunnel there is a slag heap which sits on top of a mixture of natural soil and rock. This increases the risk of landslips and rocks falling onto the lines.

Now engineers are using large drills to drive more than 3,600 huge soil nails into the walls of the cutting to strengthen the ground for the next 120 years.

Luke Swain, Network Rail senior asset engineer for geotechnics, said: “The cutting by the Arley Tunnel is very steep so this is a really challenging job. The nearby hills are former slag heaps from the mining industry which means the earth is unusual and can become unstable.

“This vital upgrade as part of Britain’s Railway Upgrade Plan will improve the reliability of trains for passengers and will secure the railway for generations to come.”

Nine hundred metres of new drainage, 1.2 km of fencing and netting to stop anything else from falling onto the track will also be installed as part of the £6m upgrade.

No trains will be disrupted during the work.

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Network Rail press office - North West & Central Region
07740 782954
NWCmediarelations@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk