£100m INVESTMENT SIGNALS NEW START FOR NOTTINGHAM: Signal

Thursday 19 Jul 2012

£100m INVESTMENT SIGNALS NEW START FOR NOTTINGHAM

Region & Route:

The railway infrastructure in Nottingham stands on the brink of big changes, from new and refurbished station buildings, to a complete redesign of the tracks and signals.

Network Rail is embarking on a £100m plan to completely renew the railway around the city, with the relaying of six miles of track, and the installation of more than 140 new signals. Also, this week the government announced plans to electrify the line to Nottingham.

Three signal boxes and two footpath crossings will be closed, bringing greater efficiency and safety to the line, and two level crossings to the east will be renewed.

Network Rail’s resignalling work will bring a faster and more reliable railway infrastructure – as well as a new platform created at the station. This will complement the Nottingham Hub Project which is set to start in September and will deliver better station facilities at Nottingham.

Network Rail route managing director Martin Frobisher said: “This investment in Nottingham will bring a huge improvement for passengers. Nottingham is such an important city in the east midlands and the station improvements will create the gateway which the city deserves. The improvements to the railway infrastructure will improve the flexibility, speed and reliability of the services to and from the city."

As a result of the scale and complexity of the works, there will be some major changes to East Midlands Trains services between 20 July 2013 and 26 August 2013. The full timetable for the period is currently being finalised, however the following changes are expected to take place:
- no London services will be able to serve Nottingham station and will instead be starting and terminating at East Midlands Parkway station with connecting replacement bus services.
- in addition, services between Nottingham and Skegness will be affected, with services starting and terminating at Grantham during part of the work
- other services to/from Nottingham will be affected during the work and details will be confirmed at eastmidlandstrains.co.uk in advance of work starting.

Mr Frobisher added: “We realise this will cause disruption to passengers and have made every effort to minimise the length of time our resignalling will take. As the summer is the quietest period for the railway, this is the best time to do the work. We have worked very closely with the cricket ground to make sure that the railway improvement work does not conflict with the Ashes test match. A full timetabled train service will operate throughout the test match.”

When the signals are commissioned on August 24 and 25 2013, it will mark the end of Trent power signal box after 44 years of service. The area will come under the control the latest generation of signal control centres at Derby, delivering greater reliability and efficiency.

David Horne, managing director of East Midlands Trains, said: “We are pleased that Network Rail will be making this investment in the railway at Nottingham. We will be working closely with them over the next year to prepare for the major work and keep our passengers informed about the changes they can expect to their service in Summer 2013 when this important improvement work will be carried out.”

Notes to editors

Network Rail route managing director Martin Frobisher will be available for interview for a short period on Thursday, July 19.
This will be from 11am-noon at Nottingham station.

Funding for the scheme comes from Network Rail and the Office of Rail Regulation.

Work on the resignalling has already begun, with some signal gantries put in place.

The resignalling is part of a wider scheme, which will see the station’s historic porte cochere turned into a new entrance hall, and a southern entrance constructed. This will link to the Nottingham tram station, being built on a bridge over the railway. Pictures of the station plans are available on the Media Library section of our website.

Network Rail is working in partnership with Nottingham City Council and East Midlands Trains on the Hub station project itself. Construction will begin in September this year and will be finished in December 2013. Nottingham’s tram project is due for completion in late 2014.

Nottingham Resignalling at a glance:

1 new platform in the station.

143 new signals.

6 miles of new track.

3 signal boxes and Trent power signalbox closed and replaced with 2 new workstations at Derby signalling centre.

2 level crossings renewed

2 level crossings closed and replaced with footbridges.

All signalling is designed with electrification in mind so disruption will be reduced when the wires come to Nottingham.

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Network Rail press office -London North Eastern & East Midlands route
01904 383180
mediarelations@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk