Network Rail’s Anglia route comprises over 1,700 miles of track from London Liverpool Street station to Norwich in the east and Cambridge in the west, the North London Line from Gospel Oak to Barking East, and Essex Thameside from Fenchurch Street to Shoeburyness. With over 63.6 million passenger journeys, Liverpool Street is the third busiest railway station in Britain and the route is well connected with two airports, Stansted and Southend.
Latest news for this route
Transformation of Wherry lines continues with autumn works at Reedham junction
Network Rail is preparing to deliver the next phase of works to upgrade the signaling systems and track as part of the £68m Norwich, Yarmouth, Lowestoft (NYL) re-signalling project. Engineers will continue to upgrade some of the oldest signals in the country, improving safety and journeys for passengers travelling on the Wherry lines.
Major rail upgrades completed at Colchester to make main line services more reliable
Major upgrades have been carried out at Colchester to make the busy Norwich to London main line more reliable and resilient.
Reliability improvements following major upgrades on Norwich to London main line
Network Rail engineers completed an array of improvements on the Norwich to London main line over the three-day bank holiday weekend to make rail services more reliable as part of the company’s Railway Upgrade Plan.
Network Rail gets green light to enable more freight along Felixstowe branch line
Network Rail has secured permission to build a new bridleway bridge across the Felixstowe branch line to provide a safe public route across the railway while enabling for more goods to be moved by rail freight and improving reliability for passenger services.
Work to install new track between Lea Bridge and the new Meridian Water station 80% complete
Work to install a new track on the West Anglia main line as part of Network Rail’s £170m Lee Valley Rail programme is 80% complete. The project has reached a key milestone with over 4.4km of track installed on what will become the third line between Lea Bridge and the new Meridian Water station, allowing two additional trains per hour.
Southend Victoria line set for installation of 19km of new overhead wires this autumn
A total of 19km of new overhead wires is planned to be installed between Mountnessing and Wickford on the Southend Victoria branch line over the coming months, as part of a £46m upgrade to replace the overhead wiring system.
Major track upgrade for Norwich to London passengers this August bank holiday and Autumn
Vital track improvements will take place between Manningtree and Witham this August bank holiday weekend and over the Autumn months, to improve reliability for thousands of passengers using main line services every day.
Chalkwell station footbridge reopens following repairs
The footbridge at Chalkwell station on the line between Fenchurch Street and Shoeburyness reopened today (Friday 27 July) following repair and strengthening work.