Signal box moves home as part of £21m investment in Arun Valley line: Billingshurst signal box is lifted onto the back of a low-loader

Monday 24 Mar 2014

Signal box moves home as part of £21m investment in Arun Valley line

Region & Route:
| Southern

A Victorian signal box took to the skies under a crane in the early hours of Sunday morning, marking the culmination of a £21m investment in the railway through the Arun Valley.

Billingshurst signalbox is one of three to have been taken out of use last week as signalling is upgraded on the line between Horsham and Arundel.

By replacing Victorian-era signalling systems with the most modern equivalent, Network Rail has been able to shorten the distances between signals, which means that trains can safely run closer together.

Network Rail’s route managing director for Sussex, Tim Robinson, said: "The work we have completed in the Arun Valley increases the capacity of the railway, giving us more room to run trains, and do that more reliably.

"It also replaces old, and in some cases, Victorian equipment with their modern equivalent, offering new standards of reliability and efficiency."

The railway through the Arun Valley is now controlled from the area signalling centre at Three Bridges and will shortly move into a state-of-the-art control centre which recently opened at Three Bridges.

Billingshurst signal box, which is thought to date from 1868, moved to the Amberley museum on the back of a lorry on Sunday. Pulborough and Amberley signal boxes have also been taken out of use but will stay where they are.

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Network Rail press office - South East route
020 3357 7969
southeastroutecomms@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk