Passengers to benefit from £80m rail investment in the Brighton main line: Upgrading the Brighton Main Line

Thursday 2 Jan 2014

Passengers to benefit from £80m rail investment in the Brighton main line

Region & Route:
| Southern

The railway between London and Brighton has been significantly upgraded over Christmas and the New Year thanks to an £80m package of improvements completed by Network Rail.

More than 150 railway workers and engineers worked round the clock between Christmas Day and Thursday 2 January to upgrade the railway at Gatwick Airport, London Victoria station and a major junction between Redhill and Purley.

The investment will deliver long-term benefits to passengers which include a more reliable infrastructure, which will help to reduce disruption, and an additional platform at Gatwick Airport which will provide greater flexibility for services calling at the station from February 2014.

Tim Robinson, Network Rail’s route managing director for the Sussex route, said: “These three significant upgrades are part of our commitment to deliver a safer, more efficient and reliable railway which meets the increasing demands placed on it by a growing number of passengers.

“The three complex and challenging pieces of work were carried out simultaneously, which helped to minimise the level of disruption to passengers. After many months of meticulous planning, and the hard work and dedication of our staff during some fairly atrocious weather conditions, the railway was upgraded and reopened on time as planned.

“I would like to thank passengers for their patience while we completed this essential work and can assure them that we will continue to work with our partners and invest in the Sussex route to provide passengers with an ever improving service.”

Adrian Witherow, head of terminals at London Gatwick, said: “Passengers are our number one priority and we have worked closely with the train operating companies and Network Rail to help minimise any disruption to travellers over the festive period. The upgrades will make for a much improved passenger experience – for both arriving and departing travellers who will be using rail services.”

David Scorey, Southern’s operations director, said: “We would like to thank our passengers for their patience and understanding while these vital improvements took place over the festive period. which has much improved the infrastructure on key areas of the Brighton Main Line, which we expect will help to deliver performance improvements in the future”

Keith Jipps, First Capital Connect's customer service director, said: "This work had a major impact on our services, adding up to 90 minutes to passengers' journeys. I'm delighted it has been completed successfully and really pleased by how we've worked together as an industry to make sure we warned people in good time."

The improvements at the three locations included:

  • A new platform and associated track and signalling work at Gatwick Airport station which will provide greater flexibility for train services calling at the station which has potential to reduce delays caused by congestion on this busy line. Around 1300m of track was laid, a 50m long footbridge was renewed and a 250m long new platform, complete with a new lift, escalators and high-level walkway to the station, was completed. The new platform will become operational in February.
  • A major junction replacement between Redhill and Purley (Stoats Nest junction) which has removed the need for speed restrictions and increased the reliability of the infrastructure. Replacing Stoats Nest junction was a huge engineering challenge. A total of 16 separate switches and crossings were replaced which, if they were laid end to end, would be around one mile long. More than 350 separate welds were used to complete the work. Around 7,770 tonnes of spoil were removed and replaced using 21 trains to transport the material.
  • New signalling between London Victoria and Battersea, building on previous work carried out by Network Rail to upgrade the infrastructure and provide a more reliable service. Work took place at more than 70 separate locations and 12 new signals were installed.

Notes to editors

In addition to the improvement work carried out over the festive period, Network Rail’s Sussex route team have also had to deal with damage caused by recent storms.

Two landslips at Redhill and Coulsdon, caused by last week’s rain storms, have been repaired along with flood and fire damage to the track at West Croydon, and flooding near Balcombe.

A serious landslip at Ockley, between Horsham and Dorking, will take longer to rebuild with services unlikely to resume until February.

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Network Rail press office - South East route
020 3357 7969
southeastroutecomms@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk