Ministers review West Coast Mainline recovery works

Friday 8 Jan 2016

Regions: 54c2493766ac95135c1db35e
Ministers review West Coast Mainline recovery works: Lamington Viaduct - UK Rail Minister Claire Perry, Network rail MD for ScotLand Phil Verster (centre) and Scottish Transprt Minister Derek Mackay review recovery works

UK Government Rail Minister Claire Perry and Scottish Government Transport Minister Derek Mackay joined Network Rail managing director for Scotland Phil Verster at Lamington today to see the ongoing operation to repair a vital viaduct on the West Coast Mainline.

Engineers are currently working around-the-clock to stabilise the structure after one of its stone piers was badly weakened by floodwater damage caused by Storm Frank.

Over 1,500ton of stone has been used to create a temporary dam across part of the River Clyde to allow engineers to access the base of the pier, where large sections of the original stone foundations have been washed away.

Over the weekend, engineers will pump around 150tons of quick-setting concrete into the void to recreate the pier base before beginning additional work to strengthen the structure and realign and repair the railway track above.

The recovery works are currently progressing to plan and engineers are continuing to target February 1 for the reopening of the line for passengers.

Phil Verster, Network Rail managing director for Scotland, said: “Our engineers are working hard in very challenging conditions to stabilise and strengthen the structure.

“The West Coast Mainline is a vitally important transport link for passengers and freight and we are committed to completing these works and reopening the line for customers as quickly as we can.”

UK Government Rail Minister Claire Perry said: “The storms and extreme weather conditions in recent weeks have resulted in great challenges for the transport system across the UK. We are working closely with Network Rail and the train operators to make sure that the considerable damage to the viaduct is repaired as soon as possible so that the line can be reopened, and we thank them for their hard work. I am determined that the safety of passengers and workers must always be our priority while this work is ongoing.

“I’d also like to thank customers for their patience during this period of disruption. The UK Government is working with the industry to ensure passengers are kept informed and alternative travel options are provided wherever possible. Passengers wishing to travel should contact their train operator for advice and plan their journeys in advance. We continue to monitor the situation closely to ensure it is safely opened as soon as possible.”

Scottish Government Transport Minister Derek Mackay said: “The record amount of rainfall that we have witnessed over recent weeks has resulted in significant damage to transport infrastructure around Scotland, including the West Coast and Highland main lines.

“I recognise the inconvenience that these works are causing to passengers, however, the safety of Scotland’s railways is of paramount concern and the severity of the damage to the viaduct meant that engineers were left with no option but to suspend all services that use it. I can assure the public that Network Rail are doing all they can to get the rail service operational again under difficult conditions.

“The Scottish Government is working closely with the rail industry to ensure that repairs are being carried out as quickly, safely and efficiently as possible and that passengers are being kept informed of the most appropriate methods of alternative travel. I would like to thank the public for their cooperation and understanding.”

While work to repair Lamington Viaduct continues, Virgin Trains will be running a shuttle service between Glasgow Central and Carlisle, via the Dumfries line, to connect passengers back into the West Coast Mainline.

At the same time, it has been confirmed that work to upgrade the East Coast Mainline between Newcastle and Darlington over coming weekends in January will go ahead with Network Rail (NR) and the Train Operating Companies (TOCs) working together to help passengers make cross border journeys.

Journeys between Edinburgh Waverley and London King’s Cross will run via a diversionary route and travel times will be extended.

Passengers who are planning to travel on either the East or West Coast Main Lines or via trans-Pennine routes are advised to check with their train operator before they travel but can be confident that they will be able to make their journey although it might take them longer or be by an unfamiliar route. 

Phil Bearpark, Virgin Trains’ Executive Director of Operations and Projects on the West Coast route, said: ‘We’re really sorry for the inconvenience that this closure of the West Coast Main Line has caused for our customers. Safety is of paramount importance to the railway and we fully support Network Rail as they work to get the route back into use.

“We’ve worked really hard with our industry partners in the ScotRail Alliance to put in place a diversionary service between Glasgow and Carlisle via the Dumfries route and are really pleased that, from Sunday, frequencies will increase to hourly throughout most of the day. Journeys for customers travelling to Carlisle and onwards stations, including London, will still take just over an hour longer than normal but will mean that most of our customers will no longer have to use buses. This is a great example of the industry coming together and working collaboratively in the interests of passengers.

“Naturally anyone who has had to cancel their journey due to this disruption will be entitled to a full refund.”

Warrick Dent, Safety and Operations Director for Virgin Trains on the east coast route, said: “Network Rail is carrying out critical upgrade works on the East Coast Main Line over the next four weekends which will result in extended journeys for our customers.

“There’s never a good time to upgrade such a busy route but this work is vitally important to ensure the timely and reliable operation of the railway.”

First TransPennine Express Operations Director Paul Watson added: “Despite the damage to the viaduct we are still able to move customers to and from Scotland. We’re currently providing rail replacement coaches in both directions between Edinburgh and Lockerbie, and in both directions between Glasgow and Carlisle. We understand this will add more journey time and we know it’s a frustrating situation; however we are providing the best service we can in these difficult circumstances and we will continue to get customers to their destination. We are asking all customers to check ahead before they travel and use our website to get the latest information on our services.”


Contact information

Nick King
Media relations manager (Scotland)
Network Rail
0141 555 4108 / 07515 617073

About Network Rail

Network Rail owns, manages and develops Britain's railway - the 20,000 miles of track, 40,000 bridges and viaducts and the thousands of signals, level crossings and stations (the largest of which we also run). In partnership with train operators we help people take more than 1.65bn journeys by rail every year and move hundreds of millions of tonnes of freight, saving almost 8m lorry journeys. We employ 36,000 people across Britain and work round-the-clock, each and every day, to provide a safe, reliable railway.

About the Railway Upgrade Plan

The Railway Upgrade Plan is Network Rail's investment plan for Britain's railways. It makes up two-thirds of Network Rail's £40bn spending priorities for the five years to 2019 and represents the biggest sustained programme of rail modernisation since the Victoria era. It is designed to provide more capacity, relieve crowding and respond to the tremendous growth Britain's railways continue to experience; passenger numbers have doubled in the past 20 years and are set to double again over the next 25 years - so we need to continue to invest in building a bigger, better railway. For passengers, that means:

  • longer, faster more frequent trains;
  • better, more reliable infrastructure; and
  • better facilities for passengers, especially at stations.

Follow us on Twitter: @networkrailPR
Visit our online newsroom:


Lamington Viaduct - UK Rail Minister Claire Perry, Network rail MD for ScotLand Phil Verster (centre) and Scottish Transprt Minister Derek Mackay review recovery works

Lamington Viaduct - UK Rail Minister Claire Perry, Network rail MD for ScotLand Phil Verster (centre) and Scottish Transprt Minister Derek Mackay review recovery works

View | Download

Lamington Viaduct 3 - Claire Perry, Derek Mackay and Phil Verster view the dam from track level

Lamington Viaduct 3 - Claire Perry, Derek Mackay and Phil Verster view the dam from track level

View | Download

Lamington viaduct-4

Lamington viaduct-4

View | Download