More housing and more train passengers – Network Rail sets out 30-year plan to cater for growth in south east London and Kent: London Victoria , Battersea and Grosvenor carriage sidings

Tuesday 14 Mar 2017

More housing and more train passengers – Network Rail sets out 30-year plan to cater for growth in south east London and Kent

Region & Route:
| Southern

Plans to make sure the railway can continue to accommodate huge growth in passengers and freight in south east London and Kent have been published by Network Rail – and you can have your say.

With passenger numbers on railway lines connecting the capital with Kent forecast to rise by 47% by 2044 – and a massive 127% on high speed trains to and from St Pancras International – Network Rail has worked with its industry partners to create a draft strategy to keep people moving over the next 30 years.

Housing and jobs growth in the region are continuing their upward trend and many parts of the railway into central London – including routes to and from Cannon Street, St Pancras International, and Charing Cross stations – are already completely full at peak times, with no more space for additional trains.

While immediate forecast growth can be met through lengthening trains to 12 carriages, more radical and challenging solutions will be needed in the longer term. This includes expanding central London stations, most notably Charing Cross.

The Kent Area Route Study draft has been produced to help solve that immediate challenge and provide a range of solutions for the next 30 years. With a new passenger train franchise for Kent due to start in 2018, the publication of the Kent Area Route Study supports a joined-up approach between potential bidders, the Department for Transport and Network Rail to meet the needs of passengers and business.

A three-month consultation period is now open to allow members of the public and stakeholders, including local authorities and businesses, to have their say.

Network Rail’s route managing director for the South East, John Halsall, said: “A bigger, better and more reliable railway is absolutely vital to support jobs housing and economic growth in Kent and south east London in the decades ahead.

“Our plan sets out how we will cater for forecast passenger growth up to the mid-2020s, primarily through longer trains at the busiest times of day. Beyond that, we need to look at more radical options to enable more frequent services and changing service patterns across the region.

“By working closely together with operators and potential funders, we can keep passengers moving well into the future.”

Among the more immediate challenges to be met, running any more trains between Tonbridge and Charing Cross in peak hours is almost impossible and any solution to cater for forecast demand will need to take that into account. Growing demand for high speed services also presents a challenge, with no room in the timetable for any extra services between Ashford and St Pancras International, without changing international services. Meanwhile major housing schemes are predicted for the North Kent routes from Dartford and a potential Garden City could be built at Ebbsfleet – which would result in further increases in passenger numbers.

Options set out in the study include:

By 2024:

  • Lengthening high speed, South London metro and Kent commuter peak time trains to 12-cars, where possible and where demand requires it.
  • Platform extensions to facilitate longer trains, including at Woolwich Dockyard and minor work at Waterloo East
  • Creating a link between High Speed 1 and the Marshlink route to facilitate faster trains to Hastings and Rye. This could include an electrification scheme or bi-mode trains that can run under diesel or electric power.
  • Increasing capacity at Cannon Street by creating a siding to stable trains. This would allow for an extra train in the high peak hour (8am-9am).
  • Crowding relief schemes at Lewisham, Peckham Rye and Denmark Hill stations to improve the passenger experience.
  • New signalling systems, including Traffic Management technology, to maximise train performance on busy sections where capacity is constrained, such as Orpington to London. Traffic Management is similar to air traffic control and is able to adapt in real time to minimise disruption.

Long term:

  • Rebuilding Charing Cross station to allow for more and longer trains to terminate there, potentially extending the platforms across the Thames.
  • Provide additional tracks on the route into Victoria to allow more and longer trains to terminate there.
  • Creating a southern link from Ebbsfleet International via Fawkham to stations on the Bromley South route.
  • Creating a link between Faversham and Ashford, a route poorly-served by road.

The purpose of the Route Study is to provide choices for organisations who may wish to invest in the railway, including but not limited to the Department for Transport.

The draft is out for consultation for three months from today,  to gather responses from the public and stakeholders such as local authorities and businesses. A final version will be produced later this year to take in to account these responses.

It will be released later today (March 14) at www.networkrail.co.uk/running-the-railway/long-term-planning/ 

Journalists can call the press office for an advance copy.

Notes to Editors

The Department for Transport has today (Tuesday, March 14) begun consultation into the next South Eastern passenger train franchise, to run from 2018 to 2026. For information and a press release into the consultation, please see the Department’s website at www.gov.uk/government/organisations/department-for-transport

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Network Rail press office - Chris Denham
Senior media relations manager
020 3357 7969
07515 626530
chris.denham@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk