Lamington recovery works enter vital new phase: Lamington looking south Feb 14

Friday 12 Feb 2016

Lamington recovery works enter vital new phase

Region & Route:
Scotland’s Railway: Scotland

Works to repair and reopen Lamington Viaduct on the West Coast Mainline are progressing ahead of schedule after engineers successfully raised the bridge-deck back into position.

Engineers completed the complex process of jacking the track, which had dropped six inches, back into alignment over the course of this week.

Over the weekend work will take place to install the steel bearings on the viaduct’s damaged second pier. A new middle bearing will be hung from the underside of the bridge-deck and a new concrete plinth added to the top of the pier.

Engineers have taken advantage of a break in the weather conditions and the earlier than expected arrival of the new, custom-made, bearing to accelerate their recovery programme.

A new date for the reopening of the line is expected to be confirmed next week, once works to install the new middle bearing and place the weight of bridge-deck back onto its supporting piers are complete.

Stewart MacPherson, route delivery director for infrastructure projects, said: “Works to reopen the viaduct are progressing well with the structural damage below the waterline of the piers now stabilised and works well underway to realign and repair the bridge-deck.

“This has been an extremely complex and challenging project for our engineers who have had to work as quickly as possible to prevent the viaduct’s collapse and complete repairs in what have been extreme weather conditions.”

The Victorian-built viaduct was severely weakened and left close to collapse by flood damage during Storm Frank on New Year’s Eve.

Engineers had to work around-the-clock to divert the River Clyde and stabilise the structure after the viaduct’s second pier was left on the brink of failure when floodwaters scoured out much of its foundations.

The incident also damaged the second pier’s steel bearings, which support the bridge-deck and track above the pier, a non-load-bearing section of the viaduct’s third pier and the structure’s north abutment.

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Network Rail press office - Nick King
Media relations manager (Scotland)
0141 555 4108 / 07515 617073
nick.king3@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk